Which one of the following describes the total overhead variance?
A) The difference between what was actually incurred and the flexible budget amount
B) The difference between what was actually incurred and overhead applied
C) The difference between the overhead applied and the flexible budget amount
D) The difference between what was actually incurred and the total production budget
Overhead Variance
The difference between the actual overhead incurred and the overhead allocated to production during a given period.
Flexible Budget
A projection of budget data for various levels of activity.
Overhead Applied
The portion of overhead costs allocated to individual products or job orders based on a predetermined rate.
- Understand the concepts of various variances related to overhead, labor, and material costs.
- Calculate total overhead variance, labor price and quantity variances, and materials price and quantity variances.
Verified Answer
BR
Learning Objectives
- Understand the concepts of various variances related to overhead, labor, and material costs.
- Calculate total overhead variance, labor price and quantity variances, and materials price and quantity variances.
Related questions
All Urban Company Produces a Product Requiring 4 Pounds of ...
Shipp Inc Manufactures a Product Requiring Two Pounds of Direct ...
Dillon Has a Standard of 2 Hours of Labor Per ...
Denmark Corporation's Variance Report for the Purchasing Department Reports 1000 ...
Clark Company Manufactures a Product with a Standard Direct Labor ...