If the schedule calls for the production of 120 units per day and 480 minutes of production time are available per day, the maximum cycle time would be 4 minutes.
Cycle Time
The total time from the beginning to the end of a process, procedure, or activity, often measured to assess efficiency.
Production Time
The duration taken to manufacture a product, from the beginning of the process to its completion.
- Calculate maximum cycle time for production schedules.