Cycle time is computed as

A) desired output divided by the daily operating time.
B) daily operating time divided by the product of desired output and the sum of job times.
C) the product of desired output and the sum of job times divided by daily operating time.
D) daily operating time divided by the scheduled output.
E) 1.00 minus station time.

Cycle Time

The total time from the beginning to the end of a process, including both processing and waiting times.

Daily Operating Time

The total time per day during which a business or system is operational and open for business.

  • Comprehend how to calculate cycle time for production processes.