Which of these statements regarding time-cost tradeoffs in CPM networks is true?

A) Crashing is not possible unless there are multiple critical paths.
B) Crashing a project often reduces the length of long-duration, but noncritical, activities.
C) Activities not on the critical path can never be on the critical path, even after crashing.
D) Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
E) None of the above are true.

CPM Networks

Critical Path Method (CPM) networks are project management tools that map tasks in a project, identifying the longest sequence of dependent tasks (critical path) to determine the shortest project duration.

Project Duration

Project duration is the total time from the initiation to the completion of a project, encompassing all phases of its lifecycle.

  • Identify the consequences of time-cost compromises in project planning and administration.