Compressing the task durations along the critical path to meet the project completion date is called _____.

A) scope creep
B) float
C) slack
D) crashing
E) expediting

Critical Path

The sequence of tasks that determines the minimum completion time for a project, where any delay will result in a delay of the entire project.

Project Completion Date

The specifically scheduled date by which all work on a project is expected to be completed.

Crashing

A project management technique that involves adding additional resources to critical tasks to shorten the project duration.

  • Comprehend the effect of timing on the alterations in project costs and scope.
  • Understand the principles of critical path, total float, and project duration.