To consider the availability of team members, consultants, and key pieces of equipment, you can create an) _____ which indicates working days and days off for a group or individual.

A) resource calendar
B) project calendar
C) task calendar
D) hierarchical calendar
E) base calendar

Resource Calendar

A calendar that documents the availability, working hours, holidays, and assignments of resources necessary for project completion.

Working Days

Days designated for work, typically excluding weekends and public holidays.

  • Define and explain the different components and aids used in the crafting of project timelines, including milestones, calendars, and schedules.
  • Grasp the significance of resource allocation and leveling in the context of project management.