The Gantt chart:
A) is usually difficult to read and analyze.
B) is also called a PERT chart.
C) is used to indicate duration and relationships between project activities.
D) illustrates complex relationships well.
E) is a time-scaled graphic that represents each activity with connected straight line segments.
Gantt Chart
A visual tool for project planning that displays activities against time, often used for tracking project schedules.
- Recognize and delineate various elements and instruments utilized in planning a project, including milestones, calendars, and schedules.
- Comprehend the procedure for revising and managing the project timetable to efficiently oversee time.
Verified Answer
DU
Learning Objectives
- Recognize and delineate various elements and instruments utilized in planning a project, including milestones, calendars, and schedules.
- Comprehend the procedure for revising and managing the project timetable to efficiently oversee time.
Related questions
To Consider the Availability of Team Members, Consultants, and Key ...
The _____ Is a Technique for Graphically Displaying the Logic ...
An) _____ Has No Duration or Resources, and Is Simply ...
Which of the Following Is NOT True About a Master ...
The _____ Is the Process of Determining the Earliest Starting ...