_____ the schedule is a term used to describe the various techniques used to shorten the project schedule.
A) Benchmarking
B) Crashing
C) Decompressing
D) Slacking
E) Floating
Crashing
An approach in project management to shorten the project schedule by adding resources to critical tasks.
- Identify the methods and rationale behind accelerating a project schedule.
Verified Answer
AA
Learning Objectives
- Identify the methods and rationale behind accelerating a project schedule.