The _____ is the sequence of activities through the network that results in the latest completion date of the project.
A) master schedule
B) alignment process
C) milestone schedule
D) rough order of magnitude
E) critical path
Critical Path
The sequence of stages determining the minimum time needed to complete a project, where any delay could cause the project to be delayed.
- Apprehend the rudimentary notions of project scheduling and planning.
- Realize the importance of accurately identifying connections between activities in project planning ventures.
Verified Answer
NP
Learning Objectives
- Apprehend the rudimentary notions of project scheduling and planning.
- Realize the importance of accurately identifying connections between activities in project planning ventures.
Related questions
Activities That Have Predecessor-Successor Relationships Occur _____ ...
The _____ Is a Technique for Graphically Displaying the Logic ...
If Activities Must Begin at the Same Time, They Have ...
The Most Detailed Versions of the Schedule May Be Developed ...
The Relationship Between a Predecessor Activity and a Successor Activity ...