Asked by

makenna harmsen
on Oct 19, 2024

verifed

Verified

The amount of time that must separate the finish of one activity and the beginning of the next sequential activity is called _____.

A) lead time
B) system time
C) lag time
D) cycle time
E) saved time

Lag Time

The delay between tasks that have a dependency, where one task cannot start until a certain period after the previous task has finished.

  • Gain an understanding of the notions of lead, lag, and float times and how they impact the planning of project timelines.
verifed

Verified Answer

RA
Rochelle AnchetaOct 23, 2024
Final Answer:
Get Full Answer