_____ is the difference between the finish date of the last activity on the critical path and the project completion date.

A) Lag time
B) Control limit
C) Total float
D) Contingency time
E) Forward pass

Total Float

The amount of time that a project task can be delayed without causing a delay to the project's overall completion date.

  • Understand the significance of establishing precise relationships between activities in project planning.
  • Comprehend the principles of lead, lag, and float times and their effects on the scheduling of projects.