Asked by

Abayneh Jemaneh
on Nov 30, 2024

verifed

Verified

Apart from cost, schedule, and specifications, what was the fourth aspect of project management added by Meredith and Mantel?

A) The risks associated with the project
B) The quality standards for the project
C) The expectations of the client
D) The expectations of the project manager
E) The code of conduct for the people working on the project

Project Management

The application of knowledge, skills, tools, and techniques to project activities to meet project requirements efficiently and effectively.

Cost

The amount of money required for the production or acquisition of goods or services, or the expenditure incurred by a business or project.

Schedule

A detailed timeline for the execution of tasks or events, specifying start and end times or dates.

  • Outline the aspects including risks and quality standards integral to project management.
verifed

Verified Answer

KS
kathya solisDec 07, 2024
Final Answer:
Get Full Answer