Risks that can be anticipated, such as exceptionally bad weather, are called _____.

A) risk events
B) uncertain risks
C) known risks
D) random risks
E) risk aversions

Known Risks

Risks that have been identified and analyzed, allowing for planned responses.

  • Acquire knowledge on how to identify and evaluate the risks involved in a project.
verifed

Verified Answer