An updated schedule that shows the present status of the project is called the _____ schedule.
A) performance index
B) master
C) milestone
D) general conceptual
E) current
Current Schedule
The latest version of the project schedule, reflecting all known updates, changes, and progress.
- Differentiate among various schedule categories (master, milestone, current) and their applications.
- Understand the process of updating and controlling the project schedule to manage time effectively.
Verified Answer
MK
Learning Objectives
- Differentiate among various schedule categories (master, milestone, current) and their applications.
- Understand the process of updating and controlling the project schedule to manage time effectively.