Asked by
Samoria Session
on Oct 27, 2024Verified
What is the latest finish time for Activity I?
A) 76
B) 110
C) 84
D) 105
Latest Finish Time
In project management, the latest possible point in time by which an activity must be completed without delaying the project.
- Identify the timelines for projects and tasks through the use of project management approaches.
Verified Answer
TM
Learning Objectives
- Identify the timelines for projects and tasks through the use of project management approaches.