The project work breakdown structure WBS) :
A) developed around the functions of the project facilitates the understanding of the amount of work required for each stage of the project.
B) represents a breakdown of the project into components that encompasses a part of the scope of the project.
C) size is directly related to the duration of each of the activities of the project.
D) represents increasing amounts of detail at its highest level while the lower levels represent broad categories.
E) is a hierarchical listing and grouping of the project activities required to produce the deliverables of the project.
Work Breakdown Structure (WBS)
A hierarchical decomposition of a project into smaller components, helping organize and define the total scope of the project.
Hierarchical Listing
An organized structure of items or information ranked and arranged strictly in order of rank, value, or authority.
- Acquire knowledge on how to carry out a master schedule by dividing major tasks and designating resources.
Verified Answer
SN
Learning Objectives
- Acquire knowledge on how to carry out a master schedule by dividing major tasks and designating resources.
Related questions
A WBS Can Be Decomposed, That Is, Separated into Basic ...
The Unit of Measure That Is Chosen for Tracking Schedule ...
To Execute the Master Schedule, the Major Activities Are Broken ...
The Higher Levels of the Work Breakdown Structure WBS) Represent ...
During the Conceptual Phase, Detail Is Required in the Project ...