The labor efficiency variance is labeled favorable (F)if the actual hours used is less than the standard hours allowed for the actual output.
Labor Efficiency Variance
The difference between the actual hours worked and the standard hours worked, multiplied by the standard labor rate.
Standard Hours
A measure used in accounting to indicate the expected amount of time required to complete a task or project.
Actual Hours
The total time spent on a specific task or job by workers, typically measured in hours.
- Examine and interpret the difference in expenses for materials, labor, and indirect costs.
- Evaluate the significance of labor rate and efficiency variations on production cost implications.
Verified Answer
BH
Learning Objectives
- Examine and interpret the difference in expenses for materials, labor, and indirect costs.
- Evaluate the significance of labor rate and efficiency variations on production cost implications.
Related questions
Variable Manufacturing Overhead Is Applied to Products on the Basis ...
If Demand Is Insufficient to Keep Everyone Busy and Workers ...
An Unfavorable Materials Quantity Variance Indicates That ...
If Skilled Workers with High Hourly Rates of Pay Are ...
A Favorable Labor Rate Variance Indicates That ...