The critical path for the network activities shown below is ________ with duration ________.  Activity  Duration  Immediate  Predecessors  A 2− B 4− C 6 A, B  D 1 A, B  E 2 B,C,D\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Duration } & \begin{array} { c } \text { Immediate } \\\text { Predecessors }\end{array} \\\hline \text { A } & 2 & - \\\hline \text { B } & 4 & - \\\hline \text { C } & 6 & \text { A, B } \\\hline \text { D } & 1 & \text { A, B } \\\hline \text { E } & 2 & \mathrm {~B} , \mathrm { C } , \mathrm { D } \\\hline\end{array} Activity  A  B  C  D  E  Duration 24612 Immediate  Predecessors  A, B  A, B  B,C,D

A) A-D-E; 5
B) B-E; 6
C) B-D-E; 7
D) A-C-E; 10
E) B-C-E; 12

Critical Path

The sequence of stages determining the minimum time needed for an operation, especially in the context of project management.

Immediate Predecessors

Tasks or activities that must be completed directly before a certain task can begin, critical for understanding dependencies in project management and scheduling.

Activity Duration

The total time taken to complete a specific activity, task, or process from start to finish.

  • Employ proficiency in Critical Path Method to scrutinize project timeframes and spotlight pivotal activities.
verifed

Verified Answer

DT
David TjuhandaDec 11, 2024
Final Answer:
Get Full Answer