On projects with a large equipment budget, the highest portion of risk may be toward the end of the project.
Equipment Budget
An estimation of the cost for acquiring machinery and equipment required for the execution of a project or operation.
- Identify the complexities and potential dangers that accompany emerging technological innovations in project settings.
Verified Answer
JR
Learning Objectives
- Identify the complexities and potential dangers that accompany emerging technological innovations in project settings.