An assembly line consists of 21 tasks grouped into 5 workstations. The sum of the 21 task times is 85 minutes. The largest assigned cycle time is 20 minutes. The efficiency of this line is
A) 4.2%.
B) 17%.
C) 85%.
D) 100%.
E) 126%.