A rate of return required by management to accept a project is called ________.

A) hurdle rate
B) net present rate
C) rate of inflation
D) payoff rate

Hurdle Rate

The minimum rate of return on a project or investment required by a manager or investor.

Rate of Return

The gain or loss of an investment over a specified period, expressed as a percentage of the investment's cost.