Filters
Question type

Distortion in MRP systems can be minimized when safety stock is held at the:


A) purchased component or raw material level.
B) work-in-process level.
C) finished goods level.
D) A and B
E) A and C

Correct Answer

verifed

verified

Which of the following is NOT a key benefit of MRP?


A) increased quality
B) better response to customer orders
C) faster response to market changes
D) improved utilization of facilities and labor
E) reduced inventory levels

Correct Answer

verifed

verified

When safety stock is deemed absolutely necessary,the usual policy is to build it into (increase)the inventory requirement of the MRP logic.

Correct Answer

verifed

verified

What do we mean by closed-loop MRP?

Correct Answer

verifed

verified

It's a system that provides fe...

View Answer

________ is a system that allows,with MRP in place,inventory data to be augmented by other resource variables.

Correct Answer

verifed

verified

Material requirement...

View Answer

Product A is made from 2 Bs and 1 C.Lead times for A,B,and C are 2,3,and 2 weeks respectively.Currently there are 2 Bs and a 5 Cs on hand,with 5 of each scheduled to arrive at the end of week 1.If 20 As are needed during week 4,can the order be completed (it is the start of week 0 currently)?

Correct Answer

verifed

verified

To produce 20 As requires 40 B...

View Answer

By convention,the top level in a product structure is designated level 1.

Correct Answer

verifed

verified

Firms may discover that,rather than adapting ERP to the way they do business,they have to adapt the way they do business to accommodate the ERP software.

Correct Answer

verifed

verified

What does the POQ interval equal?


A) the number of periods of average demand covered by the safety stock
B) the same number of periods that are on the "not to be rescheduled" side of the time fence
C) EOQ / maximum gross requirement
D) the number of periods until the incoming projected on hand runs out
E) EOQ / average demand per period

Correct Answer

verifed

verified

What does enterprise resource planning (ERP)allow an organization to do?

Correct Answer

verifed

verified

It allows the organization to automate a...

View Answer

If safety stock is desired,it should be built into which portion of MRP?


A) module level
B) purchased component
C) raw materials
D) finished goods
E) all of the above

Correct Answer

verifed

verified

Consider the following product structure. Consider the following product structure.   If the demand for product A is 50 units,how many units of component E will be needed? A) 4 B) 100 C) 200 D) 250 E) 300 If the demand for product A is 50 units,how many units of component E will be needed?


A) 4
B) 100
C) 200
D) 250
E) 300

Correct Answer

verifed

verified

The lot-for-lot lot-sizing technique is particularly appropriate when demand is not very smooth and set up cost is small compared to holding cost.

Correct Answer

verifed

verified

Four A washers,five B washers,two C bolts,and a D bolt are required to make one grill parts kit.If 100 grill parts kits are needed,how many more washers will be consumed than bolts?

Correct Answer

verifed

verified

Using MRP explosion gives A = ...

View Answer

Demand for a given item is said to be dependent if:


A) it originates from the external customer.
B) there is a deep bill of material.
C) the finished products are mostly services (rather than goods) .
D) there is a clearly identifiable parent.
E) the item has several children.

Correct Answer

verifed

verified

An order for 50 units of Product A and 60 of B has been placed.There are currently 25 units of Product B on hand.Each A requires 2 units of Part C;each B requires 5 units of C.There are 160 units of C available.What are the net requirements for C?


A) 115
B) 175
C) 240
D) 690
E) 700

Correct Answer

verifed

verified

What are time fences? Why are they used?

Correct Answer

verifed

verified

Time fences allow a segment of...

View Answer

Which of the following is FALSE concerning enterprise resource planning (ERP) ?


A) It attempts to automate and integrate the majority of business processes.
B) It shares common data and practices across the enterprise.
C) It is inexpensive to implement.
D) It provides and accesses information in a real-time environment.
E) ERP software promises reduced transaction costs.

Correct Answer

verifed

verified

MRP II is accurately described as:


A) MRP software designed for services.
B) MRP with a new set of computer programs that execute on microcomputers.
C) material resource planning.
D) an enhancement of MRP that plans for all levels of the supply chain.
E) a new generation of MRP software that extends MRP to planning and scheduling functions.

Correct Answer

verifed

verified

Describe the role of record accuracy in Wheeled Coach's successful use of MRP.

Correct Answer

verifed

verified

Wheeled Coach's record integrity is exce...

View Answer

Showing 41 - 60 of 113

Related Exams

Show Answer