A) A B C D
B) D A B C
C) C D A B
D) C B A D
Correct Answer
verified
Multiple Choice
A) The periodic order quantity (POQ) rule seeks to create inventory remnants.
B) If the POQ rule is used,an item's lot size can vary each time an order is placed.
C) The lot for lot (L4L) rule is a special case of the fixed order quantity (FOQ) rule.
D) All lot-sizing rules seek to minimize inventory levels.
Correct Answer
verified
Multiple Choice
A) One of the main prerequisites for implementing an MRP system is to have products with few BOM levels.
B) The scheduled receipts for a parent item are used to calculate the gross requirements for components of that parent.
C) Some of the key inputs to a computerized MRP system are inventory records,updated bills of material,and a valid master production schedule.
D) Benefits of a successful MRP implementation typically include a decrease in the number of inventory turns,and an increase in the number of expediters.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Release an order when there is a nonzero quantity in the first period's planned order release row.
B) Release a separate order for service parts.
C) Release an order when there is a nonzero quantity in the scheduled receipt row.
D) Release an order when the first period's gross requirements quantity is equal to zero.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) less than or equal to 80 units
B) greater than 80 units but less than or equal to 100 units
C) greater than 100 units but less than or equal to 240 units
D) greater than 240 units.
Correct Answer
verified
Multiple Choice
A) material requirements planning.
B) distribution requirements planning.
C) capacity requirements planning.
D) manufacturing resource planning.
Correct Answer
verified
Multiple Choice
A) It is computationally faster than regular MRP.
B) It is limited only to aiding order-launching decisions.
C) It incorporates informal systems through the use of expert systems technology.
D) It provides more extensive information than MRP because it is tied to the company's financial system.
Correct Answer
verified
Multiple Choice
A) document that records the most recent important actions taken in the context of MRP.
B) legal notice served by a customer whose order was delayed.
C) computer-generated document that helps make decisions about releasing new orders.
D) secret document to prompt actions to be taken against some suppliers.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) lot-for-lot (L4L) .
B) periodic order quantity (POQ) .
C) fixed order quantity (FOQ) .
D) usage quantity.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Essay
Correct Answer
verified
Essay
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) There will be exactly 2 action notices needed.
B) The planned order release quantity in week 4 is 80 units.
C) The planned receipt quantity in week 6 is 30 units.
D) The projected on-hand inventory in week 8 is 70 units.
Correct Answer
verified
True/False
Correct Answer
verified
Showing 101 - 120 of 151
Related Exams