A) 1.87 years;accept
B) 2.87 years;accept
C) 2.87 years;reject
D) 3.13 years;reject
E) 3.87 years;reject
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) it is the most easily understood valuation process.
B) the present value of the expected cash flows are equal to the cost.
C) the present value of the expected cash flows are greater than the cost.
D) it is the most easily calculated.
E) None of the above.
Correct Answer
verified
Multiple Choice
A) net present value.
B) internal rate of return.
C) payback period.
D) profitability index.
E) discounted cash period.
Correct Answer
verified
Multiple Choice
A) greater than one.
B) less than one.
C) greater than the internal rate of return (IRR) .
D) less than the net present value (NPV) .
E) greater than a pre-specified rate of return.
Correct Answer
verified
Multiple Choice
A) project B because it has the shortest payback period.
B) both projects as they both have positive net present values.
C) project A and reject project B based on their net present values.
D) project B and reject project A based on other criteria not mentioned in the problem.
E) project B and reject project A based on both the payback period and the average accounting return.
Correct Answer
verified
Multiple Choice
A) they create value for the owners of the firm.
B) the project's rate of return exceeds the rate of inflation.
C) they return the initial cash outlay within three years or less.
D) the required cash inflows exceed the actual cash inflows.
E) the investment's cost exceeds the present value of the cash inflows.
Correct Answer
verified
Multiple Choice
A) 2.05 years
B) 2.13 years
C) 2.33 years
D) 3.00 years
E) never
Correct Answer
verified
Multiple Choice
A) equal to the discount rate.
B) greater than the discount rate.
C) less than the discount rate.
D) negative.
E) positive.
Correct Answer
verified
Multiple Choice
A) The other methods help validate whether or not the results from the net present value analysis are reliable.
B) You need to use the other methods since conventional practice dictates that you only accept projects after you have generated three accept indicators.
C) You need to use other methods because the net present value method is unreliable when a project has unconventional cash flows.
D) The internal rate of return must always indicate acceptance since this is the best method from a financial perspective.
E) The discounted payback method must always be computed to determine if a project returns a positive cash flow since NPV does not measure this aspect of a project.
Correct Answer
verified
Multiple Choice
A) accept;2.03 years
B) accept;2.97 years
C) accept;3.97 years
D) reject;3.03 years
E) reject;3.97 years
Correct Answer
verified
Multiple Choice
A) greater than one.
B) greater than the cutoff point.
C) less than the cutoff point.
D) positive.
E) None of the above.
Correct Answer
verified
Multiple Choice
A) 8.95%;accept
B) 10.75%;accept
C) 8.44%;reject
D) 9.67%;reject
E) 10.33%;reject
Correct Answer
verified
Multiple Choice
A) 11.11%
B) 13.01%
C) 14.91%
D) 16.75%
E) 17.90%
Correct Answer
verified
Multiple Choice
A) net present value profile.
B) operational ambiguity decision.
C) mutually exclusive investment decision.
D) issues of scale problem.
E) multiple choices of operations decision.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) You should accept both projects since both of their PIs are positive.
B) You should accept project A since it has the higher PI.
C) You should accept both projects since both of their PIs are greater than 1.
D) You should only accept project B since it has the largest PI and the PI exceeds 1.
E) Neither project is acceptable.
Correct Answer
verified
Multiple Choice
A) $0;15.2382%
B) $3.33;27.2242%
C) $5,000;0%
D) Can not answer without one or the other value as input.
E) None of the above.
Correct Answer
verified
Multiple Choice
A) net present value profiling
B) operational ambiguity
C) mutually exclusive investment decision
D) issues of scale
E) multiple rates of return
Correct Answer
verified
Multiple Choice
A) the discount rate that makes the NPV equal to zero.
B) the difference between the market rate of interest and the NPV.
C) the market rate of interest less the risk-free rate.
D) the project acceptance rate set by management.
E) None of the above.
Correct Answer
verified
Showing 41 - 60 of 92
Related Exams