A sheet metal company has developed the following six-month production schedule in thousands of square (yards):  Week 123456 Metal 150100175200160160\begin{array} { | l | c | c | c | c | c | c | } \hline \text { Week } & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { Metal } & 150 & 100 & 175 & 200 & 160 & 160 \\\hline\end{array} In addition, their monthly labor and machine capacities in hours) available, and the production standards in hours per square yard) are: abor‾ Machine ‾ Capacity Available 16,00020,000 Prnduction Standard .10.18\begin{array}{lcc}& \underline{\text {abor}}& \underline{\text { Machine }}\\\text { Capacity Available } & 16,000 & 20,000 \\\text { Prnduction Standard } & .10 & .18\end{array} a. What is the percent utilization of the labor capacity in month 4? b. What is the percent utilization of the machine capacity in month 3? c. In how many weeks are the labor requirements over capacity?

Correct Answer

verifed

verified

a.Labor utilization:
Required capacity =...

View Answer

Lot sizing rules on a parent item do not affect the gross requirements of all lower level component items.

Correct Answer

verifed

verified

Differentiate between a level production strategy and a chase demand strategy.

Correct Answer

verifed

verified

A level production strategy plans for th...

View Answer

A company currently has no items in inventory. The demand for the next four months is 200, 400, 250 and 350 units. Assuming a level production rate of 250 units per month, determine the month in which a backorder will materialize.

Correct Answer

verifed

verified

\[\begin{array} { c c c c }
\text { Mo...

View Answer

A company is interested in developing a quarterly aggregate production plan but they aren't sure if level capacity or matching demand would be better. They have the following information available regarding their production operation: Number of working days per quarter = 65 days Number of hours per day per person = 8 hours Labor standard to produce one unit = 3 hours Demand for four quarters respectively: 40,000, 42,000, 41,000, and 44,000 units a. Using a level capacity plan, how many workers would be needed each quarter? b. For a level capacity plan, what is the beginning inventory in quarter 2? c. Using a level capacity plan, in how many quarters are the machine requirements over capacity? d. Using a matching demand plan, how many workers are needed for quarter 1? e. How many additional workers are needed in quarter 2 under a matching demand plan?

Correct Answer

verifed

verified

a. Level Capacity:
Output (40000 + 42000...

View Answer

Assigning people to tasks, setting priorities for jobs and scheduling equipment fits best with which level of the generic framework for resource planning?


A) Aggregate planning - Level 1
B) Disaggregation - Level 2
C) Execution - Level 3
D) Capacity requirements planning

Correct Answer

verifed

verified

C

A chase demand aggregate planning strategy may result in substantial overtime, undertime, and rate-change costs.

Correct Answer

verifed

verified

A company currently has no items in inventory. The demand for the next four months is 200, 400, 250 and 350 units. Determine the level production rate if a level strategy is selected with the goal of ending Period 4 with 100 units in inventory.

Correct Answer

verifed

verified

Total demand = 200 + 400 + 250...

View Answer

Lot sizing is the process of using dependent demand logic to calculate the quantity and timing of orders for all subassemblies and components that support the production of end items.

Correct Answer

verifed

verified

The lower the skill requirements of the workforce, the more feasible it is to change workforce levels as an aggregate planning option.

Correct Answer

verifed

verified

The Eugene plant of Basic Computers Inc. BCI) wants to develop a net requirements schedule for one model of microcomputers. The beginning inventory is 500 units and they like to carry 50 units as safety stock. The estimated demand for the next 6 weeks is 200, 250, 300, 375, 400, and 600 units. a. What would the net requirements be for week 3? b. What is the beginning inventory in week 5?

Correct Answer

verifed

verified

a. 300
b. 50
\[\begin{array} { | c | c ...

View Answer

A company that makes inkjet printers is trying to determine a MRP schedule for the print cartridges it needs in its newest model of printer. They have gross requirements of 1000 units in week 2 and 900 units in week 4. The minimum lot size is 500 units and the lead time is 1 week. They currently have 300 units on hand that includes a safety stock of 150 and another 100 units already allocated. They have 500 units scheduled for receipt in week 1. a. What is the number of units available in week 1? b. What is the planned order release in week 3?

Correct Answer

verifed

verified

a. 550 b. 850 \(\begin{array}{|l|r|r|r|r|} \hline\text { Week} & 1&2&3 & {4} \\ \hline \text {Gross Requirements }& & 1000 & & 900 \\ \hline \text {Schedule Receipts} & 500 & & & \\ \hline \text {Projected OH Inv.} & 550 & 550 & 50 & 50 \\ \hline\text { Net Requirements }& & 450 & & 850 \\ \hline \text {Plan Order Receipts }& & 500 & & 850 \\ \hline \text {Plan Order Releases} & 500 & & 850 & \\ \hline \end{array}\)

A paint company has the following aggregate demand requirements and cost data for the upcoming year by quarter.  Quarter  Forecast Demand units) 11,20021,50031,90041,000‾Total5,600\begin{array} { c c } \text { Quarter } & \text { Forecast Demand units) } \\\hline 1 & 1,200 \\2 & 1,500 \\3 & 1,900 \\4 & \underline { 1,000 } \\\text{Total}&5,600\end{array}  Previous quarter’s producton:  Bepinging inventory:  Backorder costs:  900 units  0units $60/ unit  Iventory holding cost  on ending inventory):  Hiring employees:  Firing employees:  $12/unit/quarter $30 unit increase $70 unit decrease \begin{array} { l c } \begin{array} { l } \text { Previous quarter's producton: } \\\text { Bepinging inventory: } \\\text { Backorder costs: }\end{array} & \begin{array} { l } \text { 900 units } \\\text { 0units } \\\$ 60 / \text { unit }\end{array} \\ \text { Iventory holding cost } & \\\begin{array} { l } \text { on ending inventory): } \\\text { Hiring employees: } \\\text { Firing employees: }\end{array} & \begin{array} { l } \text { \$12/unit/quarter } \\\$ 30 \text { unit increase } \\\$ 70 \text { unit decrease }\end{array} \\\end{array} a. Determine the change in workforce costs hiring and firing (employees) if the paint company decides to use a chase demand strategy. b. Determine the inventory holding and backorder costs for the year if the paint company wants to use a level production strategy, ending Quarter 4 with no inventory.

Correct Answer

verifed

verified

a. \[\begin{array} { c c c c } \text { Quarter } & \text { Demand } & \text { Productun Rate } & \text { Rate Change } \\ \hline 1 & 1200 & 1200 & \$ 900000 \\ 2 & 1500 & 1500 & \$ 9,000.00 \\ 3 & \text { 1900 } & \text { 1900 } & \$ 12,000.00 \\ 4 & 1000 & \begin{array} { l } \text { 1000 } \\ \end{array} &\underline{ \$63,000.00} \\&&\begin{array} { l } \text { Total } \\ \end{array} & \$63,000.00 \end{array}\] b. \[\begin{array} { c c c c c } \text { Quarter } & \text { Demand } & \text { Production Rate } & \text { Ending Inventary } & \text { Inventary/Backorder Cost } \\ 1 & 1200 & 1400 & 200 & 2 , 4 0 0 . 0 0 \\ 2 & 1500 & 1400 & 100 & \$ 1,200.00 \\ 3 & 1900 & 1400 & 400 ) & \$ 24,000.00 \\ 4 & 1000 & 1400 & 0 &\underline{ \$ 0}\\ &&&\text { Total }&\$27,600.00 \end{array}\]

Describe the options that managers have for developing aggregate plans to respond to fluctuating demand.

Correct Answer

verifed

verified

Demand Management: Marketing strategies ...

View Answer

Increasing the output rate without changing existing resources is an example of demand management.

Correct Answer

verifed

verified

The purpose of aggregate planning is to


A) Minimize the work force size
B) Maximize the production rate
C) Minimize the cost of meeting demand
D) Optimize the inventory level

Correct Answer

verifed

verified

The primary output of an MRP system is a time-phased report that gives all of the following except


A) The facilities managers a detailed schedule for acquiring additional factory space
B) The accounting and financial functions production information that drives cash flow, budgets, and financial needs
C) The production managers a detailed schedule for manufacturing the product and controlling manufacturing inventories
D) The purchasing department a schedule for obtaining raw material and purchased items

Correct Answer

verifed

verified

Which of the following is not correct regarding aggregate planning?


A) Large number of alternatives
B) Good solutions by trial-and-error method
C) Seasonal fluctuations in demand
D) Costs are sunk and irrelevant

Correct Answer

verifed

verified

The words "product family," "budget allocation" and "long-term" fit best with which level of the generic framework for resource planning?


A) Aggregate planning - Level 1
B) Disaggregation - Level 2
C) Execution - Level 3
D) Capacity requirements planning

Correct Answer

verifed

verified

Explain the three levels of resource planning.

Correct Answer

verifed

verified

Level 1 is aggregate planning, which is ...

View Answer

Showing 1 - 20 of 88