An assembly line with 28 operations is to be balanced. The total amount of time required for all 28 operations is 39 minutes. The longest operation takes 2.2 minutes and the shortest takes 0.8 minutes. The line will operate for 450 minutes per day. 1. Determine the minimun and maximu cycle time. 2. What is the output rate if the cycle tine is set at 2.2 minutes?


A) min cycle time = 0.8; max cycle time = 39; output rate = 204.5
B) min cycle time = 2.2; max cycle time = 39; output rate = 204.5
C) min cycle time = 2.2; max cycle time = 31.2; output rate = 562.5
D) min cycle time = 0.8; max cycle time = 2.2; output rate = 562.5

Correct Answer

verifed

verified

Which is true for product layout?


A) Very flexible
B) Lower work-in-process inventories
C) High job satisfaction
D) Easy to add new products

Correct Answer

verifed

verified

Self-managed teams perform entire jobs, rather than specialized assembly-line work.

Correct Answer

verifed

verified

Differentiate between a "flow blocking delay" and a "lack of work delay." How can each be reduced?

Correct Answer

verifed

verified

Flow-blocking delay occurs when a work c...

View Answer

Assembly line balancing problems involving many distinct products mixed-model line balancing) are generally easier to solve than single-model balancing problems because there are more alternatives available to assign tasks to workstations.

Correct Answer

verifed

verified

Facility layout is not only concerned with the arrangement of physical facilities, but also the material handling capabilities within the facility.

Correct Answer

verifed

verified

Assembly line balancing


A) Is a one-time activity.
B) Tries to minimize the production rate for a given number of work stations.
C) Tries to minimize the number of work stations for a given production rate.
D) Attempts to load work into early work stations.

Correct Answer

verifed

verified

Changes in goods and services for a firm's customer benefit package do not impact facility layouts.

Correct Answer

verifed

verified

The eleven tasks necessary to assemble an MP3 player along with their time in seconds) and immediate predecessors) is given below:  Task  Time in secands)  Predecessors  A 40 none  B 15 none  C 35 none  D 12 A, B  E 27 B, C  F 29 D  G 60 D. E  H 30 E  I 14 F, G  J 22 G, H  K 43‾ I. J Total327\begin{array} { c c c } \text { Task } & \text { Time in secands) } & \text { Predecessors } \\\hline \text { A } & 40 & \text { none } \\\text { B } & 15 & \text { none } \\\text { C } & 35 & \text { none } \\\text { D } & 12 & \text { A, B } \\\text { E } & 27 & \text { B, C } \\\text { F } & 29 & \text { D } \\\text { G } & 60 & \text { D. E } \\\text { H } & 30 & \text { E } \\\text { I } & 14 & \text { F, G } \\\text { J } & 22 & \text { G, H } \\\text { K } & \underline{43} & \text { I. J }\\\text{Total}&327\end{array} Using this information, determine the theoretical minimum number of work stations needed if the company wants to produce 600 units in a 9-hour 32,400 (seconds) day.

Correct Answer

verifed

verified

The cycle time must be at leas...

View Answer

Process layouts generally require less investment in equipment than product layouts because the equipment is less specialized.

Correct Answer

verifed

verified

Cycle time is related to the output rate and the available time to produce output.

Correct Answer

verifed

verified

An assembly line with 28 activities is to be balanced. The total amount of time required for all 28 activities is 39 minutes. The line will operate for 450 minutes per day. What must the cycle time be to achieve an output rate of 400 units/day?

Correct Answer

verifed

verified

CT = A/R =...

View Answer

In a product layout, a breakdown of one piece of equipment will not cause the entire process to shut down.

Correct Answer

verifed

verified

Cellular layouts are designed according to the functional characteristics of equipment much in the same fashion as process layouts.

Correct Answer

verifed

verified

A fixed position layout is based on the sequence of operations that is performed during the manufacturing of a good or delivery of a service.

Correct Answer

verifed

verified

The typical layout of facilities in a hospital would be an example of a ____ layout.


A) Product
B) Process
C) Cellular
D) Fixed position

Correct Answer

verifed

verified

A Gallup study showed that workers who are allowed to personalize their workplaces were no more productive than those who are not allowed.

Correct Answer

verifed

verified

____ is vertical expansion of job duties to give the worker more responsibility.


A) Job enlargement
B) Job rotation
C) Job enrichment
D) Job design

Correct Answer

verifed

verified

A line balancing solution has been developed for the assembly line for fertilizer spreaders at Green Grass, Inc. The desired output rate of 30 spreaders per hour will be achieved. The sum of times for all tasks performed on the line is 1200 seconds for each spreader assembled. Which of the following statements must be true?


A) The cycle time is 30 seconds per spreader.
B) The theoretical minimum number of work stations is 10.
C) If the solution calls for 12 stations, the efficiency is 80%.
D) If the solution calls for 11 stations, the efficiency is 80%.

Correct Answer

verifed

verified