Filters
Question type

Study Flashcards

A method for conducting risk factor identification that generates ideas but doesn't focus on decision making is:


A) A brainstorming meeting.
B) The Delphi method.
C) Past history.
D) Multiple assessments.

Correct Answer

verifed

verified

The pointy-haired dean gently suggested that study tour offerings be doubled in the coming three years so Dilbert dutifully explored the possibility of offering a week-long study tour to Elbonia.The globalization committee's consensus was that the probability of failure was high; after some discussion they agreed that the figure was perhaps 0.6.The consequences of failure were another matter.The cost of failure was 0.2,the schedule element was 0.1,and the reliability score was 0.1.The team was divided on what to do with the performance score.Two members were adamant that it was possibly as high as 0.7,but the other two members felt the performance score was closer to the others,in the neighborhood of 0.15.Estimate the overall project risk factor for this undertaking and offer commentary as to the efficacy of the study tour to Elbonia.

Correct Answer

verifed

verified

Using the high estimate for the performa...

View Answer

The house had almost been framed when an F-5 tornado ripped across the plains and turned the house back into a lumber pile,albeit not stacked as neatly as it was originally.The homeowner's fears of:


A) Technical risks had come true.
B) Operating risks had come true.
C) Acts of God had come true.
D) Environmental risks had come true.

Correct Answer

verifed

verified

What are the two types of contingency reserves and how are they handled?

Correct Answer

verifed

verified

Contingency reserves in financial and ma...

View Answer

The period of highest risk impact for a project risk exists primarily in the:


A) Development stage of the project life cycle.
B) Concept stage of the project life cycle.
C) Implementation stage of the project life cycle.
D) Termination stage of the project life cycle.

Correct Answer

verifed

verified

A common use of managerial contingency funds would be for:


A) Office supplies.
B) Management consulting fees.
C) A sudden increase in the price of unleaded gasoline.
D) An "act of God."

Correct Answer

verifed

verified

A project team assesses their primary risk factor's probability of failure with a maturity risk of 0.3,a complexity risk of 0.7,and a dependency risk of 0.8.The probability of failure is:


A) Less than or equal to 0.3.
B) Greater than 0.3 but less than or equal to 0.55.
C) Greater than 0.56 but less than or equal to 0.89.
D) Greater than or equal to 0.9.

Correct Answer

verifed

verified

Project risk is lowest during the:


A) Concept stage of the project life cycle.
B) Implementation stage of the project life cycle.
C) Termination stage of the project life cycle.
D) Development stage of the project life cycle.

Correct Answer

verifed

verified

Jim knew instinctively that his professor wouldn't appreciate it if he brought his single scoop of vanilla ice cream into the lecture hall with him.He could almost hear the inevitable question,"Did you bring enough for everyone?" To avert such an embarrassment,he practically inhaled his frozen confection as he raced down the hall.He had eaten ice cream in this fashion before and knew he would soon have an ice cream headache,which could be described as:


A) High in consequence and high in probability.
B) Low in consequence and low in probability.
C) Low in probability and high in consequence.
D) High in probability and low in consequence.

Correct Answer

verifed

verified

Which of these statements about the project risk analysis and management program is BEST?


A) Risk management is best handled using an ad hoc approach.
B) If a choice between accepting and transferring risk presents itself, risk should be transferred.
C) The project manager should choose a small subset of all risk management tools.
D) Multiple approaches to risk management should be integrated into a coherent, synthesized approach.

Correct Answer

verifed

verified

The programming division at ABC decides to resurrect the classic Battle of the Network Stars and is understandable concerned about the risk to their own stars,the shows they star on,and their reputation as a purveyor of fine family-oriented entertainment.After a thoughtful assessment of the probabilities and consequences of failure,the team discover that the three probabilities of failure are all equal and the four consequences of failure are all equal.Further,the overall consequence of failure is half the overall probability of failure.The overall risk factor is 0.6; what are the values for the three probabilities and the four consequences?

Correct Answer

verifed

verified

The overall project risk factor is 0.572...

View Answer

The deliverable from the focus step of the project risk analysis and management model is:


A) A clear, unambiguous, shared understanding of all key aspects of the project documented, verified, and reported.
B) A clear, unambiguous, shared understanding of all relevant key aspects of the RMP documented, verified, and reported.
C) A clear understanding of the implications of any important simplifying assumptions about relationships between risks, responses and base plan activities.
D) Clear ownership and management allocations, effectively and efficiently defined, legally enforceable in practice where appropriate.

Correct Answer

verifed

verified

What are any four common categories of risk? What is an element of each category?

Correct Answer

verifed

verified

Risks commonly fall into one or more of ...

View Answer

Sketch a 2 × 2 risk management assessment matrix and discuss the impact of each quadrant.

Correct Answer

verifed

verified

A risk management assessment matrix,as s...

View Answer

Use the failure probability and consequence scores shown in the table to determine the consequence of failure for the project.  Maturity 0.6 Cost 0.2 Complexity 0.8 Schedule 0.3 Dependency 0.6 Reliability 0.2 Performance 0.5\begin{array} { | l | l | l | l | } \hline \text { Maturity } & 0.6 & \text { Cost } & 0.2 \\\hline \text { Complexity } & 0.8 & \text { Schedule } & 0.3 \\\hline \text { Dependency } & 0.6 & \text { Reliability } & 0.2 \\\hline & & \text { Performance } & 0.5 \\\hline\end{array}


A) Greater than 0.7
B) Less than or equal to 0.7 but greater than 0.5
C) Less than or equal to 0.5 but greater than 0.3
D) Less than 0.2

Correct Answer

verifed

verified

The budget safety measures that address higher risks than task contingency are known as:


A) CYA factors.
B) Buffer stocks.
C) Managerial contingency.
D) Task offsets.

Correct Answer

verifed

verified

The overall project risk factor is known to be 0.5.The probability of dependency failure is twice the probability of complexity failure and four times the probability of maturity failure.The consequence of performance failure is twice the consequence of reliability failure,four times the consequence of schedule failure and eight times the consequence of cost failure.What is the difference between the probability of maturity failure and the consequence of cost failure?  Maturity X Cost Y Complexity 2X Schedule 2Y Dependency 4X Reliability 4Y Performance 8Y\begin{array} { | l | l | l | l | } \hline \text { Maturity } & \mathrm { X } & \text { Cost } & \mathrm { Y } \\\hline \text { Complexity } & 2 \mathrm { X } & \text { Schedule } & 2 \mathrm { Y } \\\hline \text { Dependency } & 4 \mathrm { X } & \text { Reliability } & 4 \mathrm { Y } \\\hline & & \text { Performance } & 8 \mathrm { Y } \\\hline\end{array}


A) 0.026
B) 0.033
C) 0.041
D) 0.048

Correct Answer

verifed

verified

The Farm Fresh Egg project was too great for one person to pull off.The construction costs for the coop and chicken run were enormous and the sinister threat of avian flu hung over the area like a black cloud.It was only through the combined efforts of Matsushita Chickenworks and the City of Edmond that the project would be undertaken,since they would be able to:


A) Accept the risk.
B) Minimize the risk.
C) Transfer the risk.
D) Share the risk.

Correct Answer

verifed

verified

There is always a chance that the music loving public cannot be convinced of the need to return to the 8-track format for new releases.The probability that we don't sell one million units before the holiday season is:


A) Promotion risk.
B) Market risk.
C) Organizational risk.
D) Financial risk.

Correct Answer

verifed

verified

What is the PRAM methodology and what are its salient features?

Correct Answer

verifed

verified

The PRAM (Project Risk Analysis and Mana...

View Answer

Showing 21 - 40 of 102

Related Exams

Show Answer