Filters
Question type

Study Flashcards

Bartels Corp.produces woodcarvings.It takes two hours of direct labor to produce a carving.Bartels' standard labor cost is $12 per hour.During August,Bartels produced 10,000 carvings and used 21,040 hours of direct labor at a total cost of $250,376.What is Bartels' labor efficiency variance for August?


A) $10,376 unfavorable
B) $2,104 unfavorable
C) $2,104 favorable
D) $12,480 unfavorable
E) $ 12,480 favorable

Correct Answer

verifed

verified

A company's flexible budget for 36,000 units of production showed variable overhead costs of $54,000 and fixed overhead costs of $50,000.The company actually incurred total overhead costs of $95,300 while operating at a volume of 32,000 units.What is the controllable variance?

Correct Answer

verifed

verified

* $54,000 variable o...

View Answer

Reference: 21_08 Fairfield Co. has collected the following information about its production activities for the current year: Actual costs and quantities: Direct materials used 95,000 lbs. @ $6.30 per lb. Units completed during the year, 50,000 units Standard costs and quantities: Price per lb. of direct material, $6.05 Two lbs. of direct material per unit -Prepare the journal entry to record the direct materials purchases and the issuance of direct materials into production.

Correct Answer

verifed

verified

None...

View Answer

Based on predicted production of 22,000 units,a company anticipates $15,000 of fixed costs and $27,500 of variable costs.The flexible budget amounts of fixed and variable costs for 16,000 units are:


A) $10,910 fixed and $20,000 variable.
B) $10,910 fixed and $27,500 variable.
C) $20,000 fixed and $15,000 variable.
D) $15,000 fixed and $20,000 variable.
E) $15,000 fixed and $27,500 variable.

Correct Answer

verifed

verified

Reference: 21_05 A job was budgeted to require three hours of labor per unit at $8 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $198,000. -What is the total labor efficiency variance?


A) $22,000 unfavorable
B) $16,000 unfavorable
C) $6,000 unfavorable
D) $16,000 favorable
E) $22,000 favorable

Correct Answer

verifed

verified

Identify and explain the primary differences between fixed and flexible budgets.

Correct Answer

verifed

verified

A fixed budget is prepared before an ope...

View Answer

Match the following definitions with the appropriate terms

Premises
The difference between the total budgeted overhead cost and the overhead cost that was allocated to products using the predetermined fixed overhead rate.
A planning budget based on a single predicted amount of sales or production volume; unsuitable for evaluations if the actual volume differs from the predicted volume.
Preset costs for delivering a product, component, or service under normal conditions.
A process of examining the differences between actual and budgeted sales or costs and describing them in terms of the amounts that resulted from price and quantity differences.
The difference between actual and budgeted sales or cost caused by the difference between the actual price per unit and the budgeted price per unit.
A budget prepared based on predicted amounts of revenues and expenses corresponding to the actual level of output.
The difference between actual and budgeted cost caused by the difference between the actual quantity and the budgeted quantity.
The combination of both overhead spending variances (variable and fixed) and the variable overhead efficiency variance.
A management process to focus on significant variances and give less attention to areas where performance is close to the standard.
The difference between actual cost and standard cost, made up of a price variance and a quantity variance.
Responses
Cost variance
Volume variance
Price variance
Quantity variance
Standard costs
Controllable variance
Fixed budget
Flexible budget
Variance analysis
Management by exception

Correct Answer

The difference between the total budgeted overhead cost and the overhead cost that was allocated to products using the predetermined fixed overhead rate.
A planning budget based on a single predicted amount of sales or production volume; unsuitable for evaluations if the actual volume differs from the predicted volume.
Preset costs for delivering a product, component, or service under normal conditions.
A process of examining the differences between actual and budgeted sales or costs and describing them in terms of the amounts that resulted from price and quantity differences.
The difference between actual and budgeted sales or cost caused by the difference between the actual price per unit and the budgeted price per unit.
A budget prepared based on predicted amounts of revenues and expenses corresponding to the actual level of output.
The difference between actual and budgeted cost caused by the difference between the actual quantity and the budgeted quantity.
The combination of both overhead spending variances (variable and fixed) and the variable overhead efficiency variance.
A management process to focus on significant variances and give less attention to areas where performance is close to the standard.
The difference between actual cost and standard cost, made up of a price variance and a quantity variance.

Reference: 21_02 Kermit Enterprises has collected the following data on one of its products:  Direct materials standard (4 lbs. @ $1/lb.)  $4 per finished unit  Total direct materials cost variance-unfavorable $7,500 Actual direct materials used 150,000lbs. Actual finished units produced 30,000 units \begin{array}{ll}\text { Direct materials standard (4 lbs. @ \$1/lb.) } & \$ 4 \text { per finished unit } \\\text { Total direct materials cost variance-unfavorable } & \$ 7,500 \\\text { Actual direct materials used } & 150,000 \mathrm{lbs} . \\\text { Actual finished units produced } & 30,000 \text { units }\end{array} -The direct materials quantity variance is:


A) $30,000 favorable
B) $30,000 unfavorable
C) $22,500 favorable
D) $37,500 unfavorable
E) $37,500 favorable

Correct Answer

verifed

verified

Which department is often responsible for the direct materials price variance?


A) The accounting department.
B) The production department.
C) The purchasing department.
D) The finance department.
E) The budgeting department.

Correct Answer

verifed

verified

Rising,Inc.,uses the following standard to produce a single unit of its product: Overhead (2 hrs.@ $3/hr.) = $6 The flexible budget for overhead is $100,000 plus $1 per direct labor hour.Actual data for the month show overhead costs of $150,000 based on 24,000 units of production.The overhead volume variance is:


A) $10,000 favorable
B) $12,000 favorable
C) $4,000 unfavorable
D) $16,000 unfavorable
E) $36,000 unfavorable

Correct Answer

verifed

verified

Price Company's flexible budget shows $10,710 of overhead at 75% of capacity,which was the operating level achieved during May.However,the company applied overhead to production during May at a rate of $2 per direct labor hour based on a budgeted operating level of 6,120 direct labor hours (90% of capacity) .If overhead actually incurred was $11,183 during May,the controllable variance for the month was:


A) $473 unfavorable
B) $473 favorable
C) $1,530 favorable
D) $1,530 unfavorable
E) $1,057 favorable

Correct Answer

verifed

verified

When recording variances in a standard cost system:


A) Only unfavorable material variances are debited.
B) Only unfavorable material variances are credited.
C) Both unfavorable material and labor variances are credited.
D) All unfavorable variances are debited.
E) All unfavorable variances are credited.

Correct Answer

verifed

verified

The difference between the total budgeted overhead cost and the overhead applied to production using the predetermined overhead rate is the:


A) Production variance
B) Volume variance
C) Overhead cost variance
D) Quantity variance
E) Controllable variance

Correct Answer

verifed

verified

A favorable direct materials price variance might lead to an unfavorable direct materials quantity variance because the company purchased cheap materials.

Correct Answer

verifed

verified

Reference: 21_09 This information comes from the records of Dina Co. for the current period: Reference: 21_09 This information comes from the records of Dina Co. for the current period:    Factory overhead (based on budgeted production of 24,500 units) Variable overhead $2.25/direct labor hour Fixed overhead $1.95/direct labor hour -Calculate the direct materials price and quantity variances,direct labor rate and efficiency variances,and the overhead controllable and volume variances.In each case,state whether the variance is favorable or unfavorable. Factory overhead (based on budgeted production of 24,500 units) Variable overhead $2.25/direct labor hour Fixed overhead $1.95/direct labor hour -Calculate the direct materials price and quantity variances,direct labor rate and efficiency variances,and the overhead controllable and volume variances.In each case,state whether the variance is favorable or unfavorable.

Correct Answer

verifed

verified

Direct Material:
blured image_TB6312_00_TB6312_00 D...

View Answer

The difference between actual and standard cost caused by the difference between the actual quantity and the standard quantity is called the:


A) Controllable variance.
B) Standard variance.
C) Budget variance.
D) Quantity variance.
E) Price variance.

Correct Answer

verifed

verified

Abrams,Inc.provides the following results of March's operations:  Direct materials price variance $400 F Direct materials quantity variance 2,000U Direct labor rate variance 100U Direct labor efficiency variance 1,200 F Variable overhead spending variance 400U Variable overhead efficiency variance 800 F Fixed overhead spending variance 100U Fixed overhead volume variance 600 F\begin{array}{lr}\text { Direct materials price variance } & \$ 400 \mathrm{~F} \\\text { Direct materials quantity variance } & 2,000 \mathrm{U} \\\text { Direct labor rate variance } & 100 \mathrm{U} \\\text { Direct labor efficiency variance } & 1,200 \mathrm{~F} \\\text { Variable overhead spending variance } & 400 \mathrm{U} \\\text { Variable overhead efficiency variance } & 800 \mathrm{~F} \\\text { Fixed overhead spending variance } & 100 \mathrm{U} \\\text { Fixed overhead volume variance } & 600 \mathrm{~F}\end{array} Required: a.Determine the total overhead cost variance for March. b.Applying the management by exception approach,which of the variances shown are of greatest concern? Why? c.Assuming the variances are immaterial and we close them to Cost of Goods Sold,what will the effect be on that account of these variances?

Correct Answer

verifed

verified

blured image_TB6312_00...

View Answer

Reference: 21_01 Five Rings, Inc, has collected the following data on one of its products:  Direct materials standard (4 lbs. @ $1/lb.)  $4 per finished unit  Total direct materials cost variance-unfavorable $13,750 Actual direct materials used 150,000lbs. Actual finished units produced 30,000 units \begin{array}{ll}\text { Direct materials standard (4 lbs. @ \$1/lb.) } & \$ 4 \text { per finished unit } \\\text { Total direct materials cost variance-unfavorable } & \$ 13,750 \\\text { Actual direct materials used } & 150,000 \mathrm{lbs} . \\\text { Actual finished units produced } & 30,000 \text { units }\end{array} -The actual cost of the direct materials used is:


A) $133,750
B) $150,000
C) $106,250
D) $158,750
E) $120,000

Correct Answer

verifed

verified

A company established a direct material standard of 2 pounds of material at a cost of $6 per pound for unit produced.During August the company produced 6,000 units of product.10,000 pounds of direct material which cost $6.50 per pound were used in the production process.Compute the direct material quantity variance for August.


A) $5,000 unfavorable
B) $12,000 unfavorable
C) $5,000 favorable
D) $12,000 favorable
E) $7,000 favorable

Correct Answer

verifed

verified

Reference: 21_07 Montaigne Corp. has the following information about its standards and production activity in November:  Actual total factory overhead incurred $28,175 Standard factory overhead: Variable overhead  $ 3.10 per unit& produced Fixed overhead ($12,000/6,000 estimated units to be produced)  $2 per unit  Actual units produced  4,800 units\begin{array}{llr} \text { Actual total factory overhead incurred } &\$28,175\\ \text { Standard factory overhead:} &\\ \text { Variable overhead } &\text { \$ 3.10 per unit}\\\& \text { produced}\\ \text { Fixed overhead} &\\ \text { \( (\$ 12,000 / 6,000 \) estimated units to be produced) } &\text { \( \$ 2 \) per unit }\\ \text { Actual units produced } &\text { 4,800 units}\\\end{array} -The controllable variance is:


A) $1,295U
B) $1,295F
C) $2,400U
D) $2,400F
E) $3,695U

Correct Answer

verifed

verified

Showing 121 - 140 of 179

Related Exams

Show Answer