An assembly line with 28 activities is to be balanced. The total amount of time required for all 28 activities is 39 minutes. The line will operate for 450 minutes per day. What must the cycle time be to achieve an output rate of 400 units/day?

Correct Answer

verifed

verified

CT = A/R =...

View Answer

A small electronics company assembles power supplies for use in computers, printers and Fax machines. They want to set up an assembly line to make their operation more efficient and plan to use line balancing with the longest-task-time heuristic. The demand for power supplies is 70 per hour, and the productive time per hour is 52 minutes. The following table provides details on their operation. A small electronics company assembles power supplies for use in computers, printers and Fax machines. They want to set up an assembly line to make their operation more efficient and plan to use line balancing with the longest-task-time heuristic. The demand for power supplies is 70 per hour, and the productive time per hour is 52 minutes. The following table provides details on their operation.    a.What is the cycle time? b.What is the theoretical minimum number of workstations? c.What tasks go into the first workstation? d.How many workstations are needed for the entire line? e.What is the assembly-line efficiency? a.What is the cycle time? b.What is the theoretical minimum number of workstations? c.What tasks go into the first workstation? d.How many workstations are needed for the entire line? e.What is the assembly-line efficiency?

Correct Answer

verifed

verified

a.Cycle time = 54 min per hr./80 units p...

View Answer

Assembly line balancing


A) Is a one-time activity.
B) Tries to minimize the production rate for a given number of work stations.
C) Tries to minimize the number of work stations for a given production rate.
D) Attempts to load work into early work stations.

Correct Answer

verifed

verified

CRAFT is a process layout technique that tries to improve on a current solution by exchanging two or three departments at a time to determine if total materials handling costs have been reduced.

Correct Answer

verifed

verified

Flow-blocking and lack-of-work delays can be reduced by assigning an appropriate level of capacity at each workstation.

Correct Answer

verifed

verified

The objective of assembly line balancing is to group tasks among workstations so that the amount of work assigned to each workstation is highly variable, thus maximizing flexibility.

Correct Answer

verifed

verified

A Gallup study showed that workers who are allowed to personalize their workplaces were no more productive than those who are not allowed.

Correct Answer

verifed

verified

The Florida Appliance Company is installing an assembly line to produce vacuum cleaners, and you, as an operations manager, are responsible for balancing the line. The tasks to be performed are listed, along with their times and immediate predecessors. The Florida Appliance Company is installing an assembly line to produce vacuum cleaners, and you, as an operations manager, are responsible for balancing the line. The tasks to be performed are listed, along with their times and immediate predecessors.   The company is planning to operate 2 shifts per day, 8 hours per shift. The desired output rate of the line is 480 units per day.  a.Compute the cycle time per unit in minutes. b.Compute the minimum number of workstations required. c.Use the longest-task-time heuristic to balance the assembly line. d.Compute the efficiency of your assembly line. The company is planning to operate 2 shifts per day, 8 hours per shift. The desired output rate of the line is 480 units per day. a.Compute the cycle time per unit in minutes. b.Compute the minimum number of workstations required. c.Use the longest-task-time heuristic to balance the assembly line. d.Compute the efficiency of your assembly line.

Correct Answer

verifed

verified

a.Cycle time: CT = A/R = 960/480 = 2 min...

View Answer

Product layouts offer higher flexibility with low productivity and process layouts have limited flexibility with high productivity.

Correct Answer

verifed

verified

Virtual teams are empowered work teams that assume many traditional management responsibilities.

Correct Answer

verifed

verified

Assembly line balancing problems involving many distinct products (mixed-model line balancing) are generally easier to solve than single-model balancing problems because there are more alternatives available to assign tasks to workstations.

Correct Answer

verifed

verified

Which of the following is not a common reason for facility layout studies?


A) There is significant change in demand or throughput volume.
B) A new good or service is introduced to the customer benefit package.
C) A new material supplier is used.
D) Different process, equipment and/or technology are installed.

Correct Answer

verifed

verified

What is the output rate if the cycle time is set at 2.2 minutes?


A) min cycle time = 0.8; max cycle time = 39; output rate = 204.5
B) min cycle time = 2.2; max cycle time = 39; output rate = 204.5
C) min cycle time = 2.2; max cycle time = 31.2; output rate = 562.5
D) min cycle time = 0.8; max cycle time = 2.2; output rate = 562.5

Correct Answer

verifed

verified

For a given cycle time in line balancing, assembly-line efficiency can be increased by


A) Speeding the line
B) Slowing the line
C) Decreasing the number of work stations
D) Increasing the number of work stations

Correct Answer

verifed

verified

Which is not true regarding fixed-position layout?


A) Synonymous with project
B) High demand volume
C) An example is a sporting event
D) Used with large items

Correct Answer

verifed

verified

Product layouts are less flexible than process layouts.

Correct Answer

verifed

verified

The determination of specific job tasks and responsibilities is called ____.


A) Job design
B) Ergonomics
C) Job enlargement
D) Job enrichment

Correct Answer

verifed

verified

In a product layout, a breakdown of one piece of equipment will not cause the entire process to shut down.

Correct Answer

verifed

verified

Cycle time is related to the output rate and the available time to produce output.

Correct Answer

verifed

verified