A) -0.0977 percent, reject
B) -9.77 percent, reject
C) -24.41 percent, reject
D) 24.41 percent, accept
Correct Answer
verified
Multiple Choice
A) Accept both A and B
B) Accept neither A nor B
C) Accept A, reject B
D) Reject A, accept B
Correct Answer
verified
Multiple Choice
A) Accept both A and B
B) Accept neither A nor B
C) Accept A, reject B
D) Reject A, accept B
Correct Answer
verified
Multiple Choice
A) The project's MIRR is 14.77 percent and the project should be accepted.
B) The project's MIRR is 9.29 percent and the project should be rejected.
C) The project's MIRR is 13.76 percent and the project should be accepted.
D) The project's MIRR is 15.31 percent and the project should be accepteD.
Correct Answer
verified
Multiple Choice
A) Discounted payback = 4.29 years; accept the project
B) Discounted payback = 3.97 years; accept the project
C) Discounted payback > 4.5 years; reject the project
D) Discounted payback = 4.4 years; accept the project
Correct Answer
verified
Multiple Choice
A) 30.10 percent
B) 29.83 percent
C) 22.47 percent
D) 31.38 percent
Correct Answer
verified
Multiple Choice
A) MIRR.
B) profitability index.
C) discounted payback.
D) NPV.
Correct Answer
verified
Multiple Choice
A) Payback = 4.44 years; reject
B) Payback = 3.44 years; accept
C) Payback = 3.54 years; reject
D) Payback = 3.24 years; reject
Correct Answer
verified
Multiple Choice
A) 1
B) 2
C) 3
D) 4
Correct Answer
verified
Multiple Choice
A) Payback
B) Discounted payback
C) Net present value
D) Profitability index
Correct Answer
verified
Multiple Choice
A) either project if they both are more than managers' maximum payback period.
B) neither project if they both are less than managers' maximum payback period.
C) the project that pays back the soonest.
D) the project that pays back the soonest if it is equal to or less than managers' maximum payback period.
Correct Answer
verified
Multiple Choice
A) NPV.
B) payback.
C) discounted payback.
D) All of these answers are suitable for firms facing time constraints.
Correct Answer
verified
Multiple Choice
A) The project's MIRR is 10.29 percent and the project should be rejected.
B) The project's MIRR is 12.67 percent and the project should be rejected.
C) The project's MIRR is 17.17 percent and the project should be accepted.
D) The project's MIRR is 18.19 percent and the project should be accepteD.
Correct Answer
verified
Multiple Choice
A) -$639.96
B) $360.04
C) $392.44
D) $486.29
Correct Answer
verified
Multiple Choice
A) MIRR.
B) profitability index.
C) payback.
D) NPV.
Correct Answer
verified
Multiple Choice
A) Payback period
B) Discounted payback period
C) Modified internal rate of return
D) Net present value
Correct Answer
verified
Multiple Choice
A) Accept both A and B
B) Accept neither A nor B
C) Accept A, reject B
D) Reject A, accept B
Correct Answer
verified
Multiple Choice
A) 2.49 years, accept
B) 2.98 years, accept
C) 3.49 years, reject
D) 4.98 years, reject
Correct Answer
verified
Multiple Choice
A) time or resource constraints.
B) a labor union.
C) the election of a new board of directors.
D) a major investment.
Correct Answer
verified
Multiple Choice
A) NPV = $1,766.55; accept the project
B) NPV = $892.19; accept the project
C) NPV = $1,288.94; accept the project
D) NPV = -$104.73; reject the project
Correct Answer
verified
Showing 1 - 20 of 112
Related Exams