A) Adding specialized labor.
B) Installing new equipment.
C) Adding new facilities.
D) Adding low-skilled labor.
Correct Answer
verified
Multiple Choice
A) The smallest number of resources devoted to it.
B) The least capacity.
C) No delays in front of it.
D) The highest cost.
Correct Answer
verified
Multiple Choice
A) 140 chips/hour
B) 350 chips/hour
C) 175 chips/hour
D) 200 chips/hour
Correct Answer
verified
Multiple Choice
A) Operation
B) Delay
C) Storage
D) You are not in a process activity.
Correct Answer
verified
Multiple Choice
A) Short-term
B) Medium-term
C) Long-term
D) It is not part of the capacity planning process.
Correct Answer
verified
Multiple Choice
A) Utilization is 60 percent of maximum capacity.
B) Yield is 133 percent of effective capacity.
C) Utilization was 133 percent of effective capacity.
D) All of these are true.
Correct Answer
verified
Multiple Choice
A) It will be able to operate at maximum capacity at all times.
B) There will be no constraints in the process.
C) Continuous improvement will not be necessary.
D) None of these are true.
Correct Answer
verified
Multiple Choice
A) One reason economies of scale occur is because fixed costs can be spread over more units of production as output increases.
B) One reason economies of scale occur is because employees become more efficient as volume increases.
C) Economies of scale refers to the fact that as volume increases, total cost of production decreases.
D) Economies of scale may not exist at all levels of production.
Correct Answer
verified
Multiple Choice
A) There is no difference - they both refer to the same concept.
B) Delays are planned activities; storages are not.
C) Delays are due to other factors; storages are not.
D) Delays require control; storages doe not.
Correct Answer
verified
Multiple Choice
A) Jidoka Event.
B) Kaizen Event.
C) Chaebol Event.
D) Poka-yoke Event.
E) Enchilada Event.
Correct Answer
verified
Multiple Choice
A) Inputs, outputs, and flows.
B) Activities.
C) Management metrics.
D) Structure.
Correct Answer
verified
Multiple Choice
A) Increasing capacity through physical additions.
B) Outsourcing.
C) Managing the flow of work into the system.
D) Changing the processes to eliminate unnecessary steps.
Correct Answer
verified
Multiple Choice
A) Delay
B) Operation
C) Storage
D) Transportation
E) Inspection
Correct Answer
verified
Multiple Choice
A) Process cost typically will go up.
B) Waiting time typically will go up.
C) Variance typically will be reduced.
D) All of these.
Correct Answer
verified
Multiple Choice
A) 15 percent
B) 50 percent
C) 85 percent
D) 100 percent
Correct Answer
verified
Multiple Choice
A) Decrease utilization.
B) Increase the coefficient of variation of job arrival times.
C) Increase the coefficient of variation of job processing times.
D) None of these would decrease waiting time.
Correct Answer
verified
Multiple Choice
A) Step 1
B) Step 2
C) Step 3
D) Step 4
Correct Answer
verified
Multiple Choice
A) Activities
B) Inputs/Outputs/Feedback
C) Process Structure
D) Management Policies.
Correct Answer
verified
Multiple Choice
A) If you don?t like the outcome, focus on the people.
B) Processes are guidelines to thinking about to best staff activities.
C) Processes drive measurement.
D) If you don?t like the outcome, change the process.
Correct Answer
verified
Multiple Choice
A) Information flows and physical flows.
B) Product flows and decision flows.
C) Information flows and operator flows.
D) Physical flows and security flows.
Correct Answer
verified
Showing 1 - 20 of 28
Related Exams