Ed is looking over the actual results of projects and comparing them to what was estimated.He notices that the projects that took six months or longer to complete were noticeably more off the estimates.Which of the following factors is he recognizing?


A) Padding estimates
B) Project duration
C) Project structure
D) People
E) Organization culture

Correct Answer

verifed

verified

While it may be true that Mega Projects are by nature extremely difficult to estimate, another factor identified in the consistent pattern of estimating difficulties is:


A) Unidentified risks.
B) Deception.
C) Economic downturn.
D) Both unidentified risks and economic downturn.

Correct Answer

verifed

verified

Top-down estimates usually are derived from someone who uses experience and/or information to determine the project duration and total cost.

Correct Answer

verifed

verified

The estimating factor that considers the decreasing accuracy of estimates as one forecasts activities that are further into the future is known as ____________.

Correct Answer

verifed

verified

planning horizon
Explanation: The qualit...

View Answer

Estimates should be based on normal conditions, efficient methods, and a normal level of resources.Explain.

Correct Answer

verifed

verified

Normal conditions are sometimes difficul...

View Answer

Which of the following would be the best method for projects where the final product is not known and the uncertainty is very large?


A) Function point
B) Template
C) Learning curve
D) Phase estimating
E) Apportion

Correct Answer

verifed

verified

Jose is forecasting project time and cost for constructing a new building by multiplying the total square footage by a given dollar amount.He is using the ___________ method of top-down estimating.

Correct Answer

verifed

verified

ratio
Explanation: Top-down methods (som...

View Answer

Laura is forecasting the time and cost of developing an intranet for a new customer.Her department has completed six such intranets for customers during the last two years.Although the proposed system is about the same size as the others, she estimates that it will take about 10 percent less time and money.Which of the following methods is she using?


A) Ratio
B) Template
C) Apportion
D) Function point
E) Learning curve

Correct Answer

verifed

verified

Organization culture can significantly influence project time and cost estimates.

Correct Answer

verifed

verified

The preferred method for situations where the cost and time estimates are important, in a fixed contract situation, and when the customer wants a lot of detail is the ___________ approach to estimating project time and costs.

Correct Answer

verifed

verified

bottom-up
Explanation: Good co...

View Answer

The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as


A) Detailed WBS work package estimates.
B) Template method.
C) Function point method.
D) Time-phased cost estimates.
E) Phase estimating.

Correct Answer

verifed

verified

Estimates that are typically based on estimates of elements found in the work breakdown structure are called bottom-up estimates.

Correct Answer

verifed

verified

Janet is forecasting how much money her department needs to support a new project.She estimates that two people and $25,000 in expenses will cover her needs.Because management typically insists on reducing forecasts by 20 percent, she increases her estimates to allow for that reduction.Which of the following factors is illustrated in this situation?


A) Padding estimates
B) Planning horizon
C) Project structure
D) People
E) Organization culture

Correct Answer

verifed

verified

A(n)__________ is something that is a valuable but burdensome possession.

Correct Answer

verifed

verified

white elephant
Expla...

View Answer

Sean is forecasting the time and cost of developing a customized software program by looking at the number of inputs, outputs, inquiries, files, and interfaces.Which of the following methods is he using?


A) Ratio
B) Template
C) Apportion
D) Function point
E) Learning curve

Correct Answer

verifed

verified

Estimating can be challenged by


A) Human Nature.
B) Political dynamics.
C) Difficulty in predicting the future.
D) All of these choices.

Correct Answer

verifed

verified

The bottom-up method of estimating where work package time and costs for past projects are used as a starting point for a new project and adjustments are made based on differences in the new project is known as the ___________ method.

Correct Answer

verifed

verified

template
Explanation: If the project is ...

View Answer

Refining Estimates may be necessary for a number of reasons.For example, a manager getting further into a project and obtaining a better understanding of what needs to be done to accomplish a project and meet the needs of the customer is an example of


A) Hidden interaction costs.
B) Things going wrong on a project.
C) Normal conditions not applying.
D) Changes in project scope.
E) There is never a good reason to refine estimates.

Correct Answer

verifed

verified

Which of the following methods is NOT considered a top-down approach to estimating project time and cost?


A) Ratio
B) Template
C) Apportion
D) Function point
E) Learning curve

Correct Answer

verifed

verified

As long as everyone in a project adds a little padding to reduce risk, the project duration and cost estimates will be more accurate.

Correct Answer

verifed

verified

Showing 81 - 100 of 101