Crashing a more expensive activity may be wise if fewer inherent risks are involved.

Correct Answer

verifed

verified

When it is necessary to reduce project duration and resources are constrained, which of the following is NOT a reasonable option?


A) Establishing a core project team
B) Fast-tracking
C) Reduce project scope
D) Compromise quality
E) Critical-chain project management

Correct Answer

verifed

verified

Creation of the ___________ graph keeps the importance of indirect costs in the forefront of decision making.

Correct Answer

verifed

verified

project cost-duration
Explanation: The p...

View Answer

What is crashing? Include a discussion of crash time and crash cost.

Correct Answer

verifed

verified

Crashing is shortening an acti...

View Answer

Brooks' law states that adding manpower to a software project helps keep it on schedule.

Correct Answer

verifed

verified

In selecting the best activity to crash you would first select the activity with the


A) Earliest start time.
B) Most steep slope.
C) Least steep slope.
D) Longest duration.
E) Largest crash time.

Correct Answer

verifed

verified

When reducing project duration, the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known.After this, the critical path must be identified.What is the next step?


A) Find the activity with the lowest crash cost
B) Calculate the optimum cost-time point
C) Calculate the crash point
D) Calculate indirect cost per time unit
E) Find the activity with the steepest cost slope

Correct Answer

verifed

verified

All of the following are disadvantages of scheduling overtime EXCEPT


A) Overtime is associated with additional costs of coordination and communication.
B) Sustained overtime work by salaried employees may incur burnout.
C) Productivity is reduced the longer one is working.
D) More hours results in higher expenses if paying workers hourly.
E) Continued overtime can lead to a higher turnover rate.

Correct Answer

verifed

verified

When the project team is salaried, which of the following is the preferred choice for accelerating project completion?


A) Assigning additional staff and equipment
B) Subcontract work
C) Schedule overtime
D) Outsource project work
E) Establish a core project team

Correct Answer

verifed

verified

The simplest way to reduce cost on a project is to reduce the scope of a project.

Correct Answer

verifed

verified

Total cost for specific project durations is computed and then compared with the benefits of reducing project time, before the project begins or while it is in progress.

Correct Answer

verifed

verified

How is the optimum cost-time point determined? What are the conditions that must exist for one to be present at a project duration other than the duration originally created under normal conditions?

Correct Answer

verifed

verified

The optimum cost-time point is the point...

View Answer

Direct costs are so named because they can be assigned directly to a work package and activity.

Correct Answer

verifed

verified

Managers have several effective methods for crashing specific project activities when resources are not constrained.

Correct Answer

verifed

verified

As a project is crashed and project duration is reduced, indirect costs typically


A) Increase.
B) Become unstable.
C) Decrease.
D) Become unreliable.
E) Stay the same.

Correct Answer

verifed

verified

Indirect costs generally represent overhead costs such as supervision, administration, consultants, and interest.

Correct Answer

verifed

verified

Because direct costs are assumed to be developed from normal methods and in a normal amount of time, any reduction in activity time should ________ the cost of the activity.

Correct Answer

verifed

verified

increase
Explanation: Because ...

View Answer

____________ is the rearranging of the project network logic so that critical activities are done in parallel rather than sequentially.

Correct Answer

verifed

verified

Fast-tracking
Explanation: Fas...

View Answer

When a project manager must reduce project duration but resources are constrained, creating a software program that will have fewer features than originally planned or building a house without the bonus room the owner originally specified in the plans would both be examples of


A) Fast-tracking.
B) Using critical-chain project management.
C) Reducing project scope.
D) Compromising quality.
E) Doing it twice-first fast and then correctly.

Correct Answer

verifed

verified

The easiest way to add more labor to a project is not to add more people, but to schedule overtime.What are the disadvantages of scheduling overtime?

Correct Answer

verifed

verified

First, hourly workers are typically paid...

View Answer

Showing 81 - 100 of 106