Activities that must occur immediately before a given activity are called ________ activities.

Correct Answer

verifed

verified

predecessor
Explanation: Activ...

View Answer

When translated into a project network,a work package will become


A) A single activity.
B) One or more activities.
C) A milestone.
D) A critical path.
E) An arrow.

F) A) and D)
G) B) and D)

Correct Answer

verifed

verified

An activity has a duration of 10 days.Its early start is 4 and its late start is 6.This activity has _____ days of total slack.

Correct Answer

verifed

verified

2
Explanation: Total slack tells us the ...

View Answer

________ slack must be coordinated with all participants in the activities that follow in the chain.

Correct Answer

verifed

verified

Total
Explanation: Total slack tells us ...

View Answer

An activity is an element of the project that always requires time.

A) True
B) False

Correct Answer

verifed

verified

Which of the following does NOT help describe a project network?


A) A graphic display of the flow and sequence of work through the project
B) Provides the basis for scheduling labor and equipment
C) Gives the times when activities can start and finish and when they can be delayed
D) Highlights major deliverables and identifies their completion dates
E) Identifies critical activities

F) C) and D)
G) A) and E)

Correct Answer

verifed

verified

Using free slack does not delay any following activities and requires no coordination with managers of other activities.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is NOT one of the basic rules to follow when developing project networks?


A) An activity cannot begin until all preceding activities have been completed
B) Each activity must have a unique identification number
C) Conditional statements are allowed but looping statements are not allowed
D) An activity identification number must be larger than that of any preceding activities
E) Networks flow from left to right

F) B) and C)
G) A) and B)

Correct Answer

verifed

verified

When completing the forward pass,the project duration is determined.A project duration of 90 days doesn't mean that if the project were to start today it would be complete in 90 days.Explain.

Correct Answer

verifed

verified

The forward pass through a project network determines the critical path.

A) True
B) False

Correct Answer

verifed

verified

What is a Gantt chart and what advantages does it have over project networks?

Correct Answer

verifed

verified

___________ reflects the likelihood the original critical path(s)will change once the project is initiated.

Correct Answer

verifed

verified

Sensitivity
Explanation: Sensitivity ref...

View Answer

Identify and briefly describe the four types of lags giving an example for each type.

Correct Answer

verifed

verified

Activities that must immediately follow a given activity are called ________ activities.

Correct Answer

verifed

verified

successor
Explanation: Activit...

View Answer