When using resource-constrained scheduling,activities that were once scheduled to be completed at the same time now may have to be scheduled in sequence.What are the "rules of thumb" or heuristics that need to be followed to determine which activity is scheduled first?

Correct Answer

verifed

verified

When considering the sequence and timing of activities,which of the following is NOT one of the types of project network constraints?


A) Physical
B) Technical
C) Resource
D) Time
E) All of these are types of constraints that could impact structure of the project network

Correct Answer

verifed

verified

A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000.Which of the following is true?


A) We are spending less than we should for the project
B) We are doing a good job managing the project
C) We should check to see if all the bills have been paid
D) We have more money to put into budget reserves
E) We can't be sure how the project is going

Correct Answer

verifed

verified

Identify and briefly describe the three types of project constraints that could impact or change the structure of project network.

Correct Answer

verifed

verified

A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000.We can assume that everything is going as planned and that we are under budget.

Correct Answer

verifed

verified

Since resource leveling or smoothing delays noncritical activities,a common result is a decrease in network sensitivity.

Correct Answer

verifed

verified

To determine if a project is time-constrained or resource-constrained you would consult the project priority matrix.

Correct Answer

verifed

verified

Project budgets are developed by time-phasing which of the following?


A) Resource schedules
B) Work packages
C) The network diagram
D) Critical activities
E) None of these are time-phased to develop a project budget

Correct Answer

verifed

verified

These are all guidelines a project manager should consider when assigning project work EXCEPT


A) Select people with compatible work habits and personalities.
B) Always assign the best people to the most difficult tasks.
C) When possible,team veterans up with new hires.
D) Select individuals with skillsets that complement each other.
E) Have people work together early so that they can become familiar with each other.

Correct Answer

verifed

verified

After constructing a project network based on technical constraints and reviewing resource requirements throughout the project,Anne realizes many peaks and valleys in regard to resource usage.At one point Anne needs 6 developers,but top management has made it very clear that she will not have access to more than 4.Classify Anne's project in terms of her scheduling problem.What are her options at this point?

Correct Answer

verifed

verified

Delaying noncritical activities to lower peak demand and,thus,increase resource utilization is called resource __________.

Correct Answer

verifed

verified

leveling or smoothing
Explanation: Pract...

View Answer

Identify and briefly describe two ways to classify projects with scheduling problems.

Correct Answer

verifed

verified

Trying to renovate a ship compartment that is too small for more than one person is an example of a(n)________ resource constraint.

Correct Answer

verifed

verified

physical
Explanation: In rare situations...

View Answer

All leveling techniques delay noncritical activities by using ________ to reduce peak demand.

Correct Answer

verifed

verified

positive slack
Explanation: Al...

View Answer

Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test.This is an example of a constraint that could impact the sequence and timing of activities in a project network.What type of constraint is it?


A) Physical
B) Technical
C) Resource
D) Scheduling
E) Time

Correct Answer

verifed

verified

If three copiers are needed to produce a final report on time and only two are available,the project is facing a(n)________ type of resource constraint.

Correct Answer

verifed

verified

equipment
Explanation: The mos...

View Answer

What are the impacts of resource-constrained scheduling?

Correct Answer

verifed

verified

Having too few programmers and too many engineers is an example of a people resource constraint.

Correct Answer

verifed

verified

If resources are not adequate to meet peak demands,the resulting reschedule is termed


A) Resource-constrained scheduling.
B) Time-constrained scheduling.
C) Mandatory leveling.
D) Project resource adjustment.
E) Allocation.

Correct Answer

verifed

verified

In a resource-constrained project,the first priority in assigning resources is usually given to activities with the


A) Smallest duration.
B) Least slack.
C) Most slack.
D) Lowest identification number.
E) Highest cost.

Correct Answer

verifed

verified

Showing 41 - 60 of 91