Filters
Question type

Study Flashcards

Activities which can take place at the same time are termed


A) Parallel activity
B) Critical path
C) Burst activity
D) Merge activity
E) Independent activity

Correct Answer

verifed

verified

The activity time estimates used to build a project network are derived from ________.

Correct Answer

verifed

verified

work packages
Explanation: A work packag...

View Answer

What is the laddering approach to project networks and why would you use this approach?

Correct Answer

verifed

verified

In laddering, lengthy activities are seg...

View Answer

Which company utilized concurrent engineering to design a new line of cars and in the process completed its development six months ahead of schedule?


A) General Motors
B) Chrysler
C) Ford
D) Nissan
E) Toyota

Correct Answer

verifed

verified

Which of the following is not one of the basic rules to follow when developing project networks?


A) An activity cannot begin until all preceding activities have been completed
B) Each activity must have a unique identification number
C) Conditional statements are allowed but looping statements are not allowed
D) An activity identification number must be larger that that of any preceding activities
E) Networks flow from left to right

Correct Answer

verifed

verified

The ________ method for creating project networks is sometimes called the Precedence Diagram Method.

Correct Answer

verifed

verified

AON or activity-on-node
Explanation: The...

View Answer

The forward pass through a project network determines the critical path.

Correct Answer

verifed

verified

Which of the following represents an activity on an AOA project network?


A) An arrow
B) A line
C) A node
D) Both A and B are correct
E) A, B, and C are all correct

Correct Answer

verifed

verified

The _________ lag is the most typical type of lag that is encountered in developing networks.

Correct Answer

verifed

verified

finish to start
Explanation: The finish-...

View Answer

Activities that can occur while an activity is taking place are called ________ activities.

Correct Answer

verifed

verified

parallel or concurrent
Explana...

View Answer

Project network logic errors include which of the following?


A) Activities with less than 1 day duration
B) Sequences such as "if test successful build prototype, if failure redesign"
C) A sequence such as B succeeds A, C succeeds B, A succeeds C
D) Both B and C are network logic errors
E) A, B, and C are all network logic errors

Correct Answer

verifed

verified

Part of a project is to Develop Product Specifications.This is best classified as a(n)


A) Event
B) Path
C) Activity
D) Node
E) Milestone

Correct Answer

verifed

verified

________ can never be negative and applies only to the last activity in a single chain of activities.

Correct Answer

verifed

verified

Free slack
Explanation: Free slack is th...

View Answer

Activities that can take place at the same time if the manager wishes them to are called ________.

Correct Answer

verifed

verified

parallel activities
Explanation: Paralle...

View Answer

In a ________ the delaying of any activity will delay the completion of the project by the same amount.

Correct Answer

verifed

verified

critical path
Explanation: Cri...

View Answer

Identify and briefly describe the four types of lags giving an example for each type.

Correct Answer

verifed

verified

1.Finish-to-Start, 2...

View Answer

Lags are used to break larger activities into smaller segments so that activities that follow can be started earlier.

Correct Answer

verifed

verified

____________ is defined as the difference between the EF of an activity and the ES of the activity that follows it.

Correct Answer

verifed

verified

A(n) ________ is the minimum amount of time a dependent activity must be delayed to begin or end.

Correct Answer

verifed

verified

lag
Explanation: A lag is the ...

View Answer

Only activities that occur at the end of a chain of activities can have free slack.

Correct Answer

verifed

verified

Showing 61 - 80 of 94

Related Exams

Show Answer