The ________ is the difference between the earned value and the actual costs for the work completed to date.

Correct Answer

verifed

verified

cost variance
Explanation: Cos...

View Answer

The network chart is the most favored, used, and understandable option for reporting project progress to upper management.

Correct Answer

verifed

verified

Earned value is calculated by taking the percent complete times the original budget.

Correct Answer

verifed

verified

Baseline project budgets are derived from:


A) The organization's overall budget
B) Time-phasing the work packages
C) Top management directions
D) Both A and C are correct
E) A, B, and C are all correct

Correct Answer

verifed

verified

A tool used to monitor past project schedule performance, current performance, and to estimate future schedule trends is a simple line chart known as a:


A) Project schedule control chart
B) Gantt chart
C) PERT chart
D) Network diagram
E) Milestone chart

Correct Answer

verifed

verified

What is the difference between a baseline Gantt chart and a Tracking Gantt chart?

Correct Answer

verifed

verified

The baseline chart is created during the...

View Answer

Earned value is defined as the budgeted cost of the work performed.

Correct Answer

verifed

verified

Interpret the results of calculating the performance indexes based on a range of possible calculated values.

Correct Answer

verifed

verified

If the index is less than one then the c...

View Answer

Measuring performance against budget is simply a case of comparing actual versus budget.

Correct Answer

verifed

verified

In a project control chart, four observations trending in one direction indicate there is a very high probability that there is an identifiable cause.

Correct Answer

verifed

verified

The percent complete index that looks at percent complete in terms of actual amounts is calculated by which of the following?


A) EV/BAC
B) (EV-PV) /BAC
C) AC/EAC
D) (EV-AC) /BAC
E) (EV-PV) /EAC

Correct Answer

verifed

verified

A typical tool used to communicate project status is a:


A) Project network diagram
B) Gantt Chart
C) A PERT chart
D) Both A and B are correct
E) A, B, and C are all correct

Correct Answer

verifed

verified

Which of the following are required to assess the current status of a project using the earned-value cost/schedule system?


A) BAC, EAC, and ETC
B) VAC, EAC, and BAC
C) CV, SU, and BAC
D) PV, EV, and AC
E) TCPI, EV, and PV

Correct Answer

verifed

verified

The ________ indexes compare the to-date progress to the end of the project.

Correct Answer

verifed

verified

percent complete
Explanation: Two projec...

View Answer

All scope changes that result in increased costs should be avoided.

Correct Answer

verifed

verified

The percent complete index that looks at percent complete in terms of budgeted amounts is calculated by which of the following?


A) EV/BAC
B) (EV-PV) /BAC
C) AC/EAC
D) (EV-AC) /BAC
E) (EV-PV) /EAC

Correct Answer

verifed

verified

The rule of using subjective estimated percent complete in combination with hard, tangible monitoring points works well on long-duration activities that can be broken into short discrete work packages.

Correct Answer

verifed

verified

CPI and SPI are two types of indexes that measure ________.

Correct Answer

verifed

verified

performance efficiency
Explanation: Ther...

View Answer

An undesirable schedule variance indicates that the project is running behind schedule.

Correct Answer

verifed

verified

A typical project progress report would contain all of the following sections except:


A) Progress since last report
B) Problems and issues since last report
C) Current status of project
D) Corrective action planned
E) All of these are typical sections

Correct Answer

verifed

verified