Using the product tree shown, determine the following: (A) the quantity of component K that will be needed to assemble 80 units of P, assuming no on-hand inventory of any components exists. (B) the quantity of component K needed to assemble 80 units of P, given on-hand inventory of 30 A's, 50 B's and 20 C's.

Correct Answer

verifed

verified

blured image A) [3 Ks per C x 2 Cs per A x 2 As per ...

View Answer

The bill of materials indicates how much material will be needed to produce the quantities on a given master production schedule.

Correct Answer

verifed

verified

One of the primary output reports of MRP concerns changes to planned orders.

Correct Answer

verifed

verified

Before a schedule receipt can take place, and order must be placed with a vendor.

Correct Answer

verifed

verified

Which one of the following is not an input in an MRP system?


A) planned-order schedules
B) bill of materials
C) master production schedule
D) inventory records
E) All are inputs.

Correct Answer

verifed

verified

A bill of materials contains a listing of all the assemblies, parts, and materials needed to produce one unit of an end item.

Correct Answer

verifed

verified

MRP II is simply an improved version of MRP that processes faster and can plan for a larger number of end items.

Correct Answer

verifed

verified

One reason that accurate bills of material are important is that errors at one level become magnified at lower levels because of the multiplication process used by MRP.

Correct Answer

verifed

verified

The master production schedule states which end items are to be produced, in addition to when and how many.

Correct Answer

verifed

verified

Net requirements equal gross requirements minus safety stock.

Correct Answer

verifed

verified

If the firm is using a fixed period lot size of two periods, what is the order size for the first order?


A) 120
B) 200
C) 280
D) 160
E) 150

Correct Answer

verifed

verified

Safety time is sometimes used in MRP rather than safety stock quantities.

Correct Answer

verifed

verified

MRP is used within most MRP II and ERP systems.

Correct Answer

verifed

verified

Periodic updating of an MRP system to account for all changes which have occurred within a given time interval is called:


A) pegging
B) planned order release
C) net change
D) regenerative
E) exception report

Correct Answer

verifed

verified

An assembly-time chart indicates gross and net requirements taking into account the current available inventory.

Correct Answer

verifed

verified

Low level coding represents items less than $18 per unit.

Correct Answer

verifed

verified

Which of the following lot sizing methods does not attempt to balance ordering (or setup) and holding costs?


A) economic order quantity
B) economic run size
C) lot-for-lot
D) part-period
E) all of the above

Correct Answer

verifed

verified

Which statement concerning MRP II is false?


A) It is basically a computerized system.
B) It can handle complex planning and scheduling quickly.
C) It involves other functional areas in the production planning process.
D) It involves capacity planning.
E) It produces a production plan which includes all resources required.

Correct Answer

verifed

verified

ERP represents an expanded effort to integrate standardized record-keeping that shares information among different areas of an organization.

Correct Answer

verifed

verified

A computer-based information system designed to handle ordering and scheduling of dependent-demand inventories is:


A) computer aided manufacturing (CAM)
B) computer integrated manufacturing (CIM)
C) economic order quantity (EOQ)
D) material requirements planning (MRP)
E) economic run size (ERS)

Correct Answer

verifed

verified