A) 120
B) 200
C) 280
D) 350
E) 450
Correct Answer
verified
Multiple Choice
A) Demand generated by suppliers.
B) Sales forecasts.
C) Derived demand.
D) Demands placed on suppliers by their customers.
E) Net material requirements.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) unstable; smooth
B) unstable; stable
C) stable; lumpy
D) smooth; sawtooth
E) sawtooth; smooth
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) I only
B) I and III only
C) I, II, IV only
D) II and IV only
E) I, II, and IV only
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) assembly time chart.
B) product structure tree.
C) MRP II.
D) pegging.
E) none of the choices.
Correct Answer
verified
Multiple Choice
A) Pegging
B) Safety stock
C) Increased order sizes
D) Safety time
E) Low-level coding
Correct Answer
verified
Multiple Choice
A) net requirements + amount on-hand.
B) gross requirements of the immediate parent(s) .
C) planned order releases of the end item.
D) net requirements of the end item.
E) planned order release of the immediate parent(s) .
Correct Answer
verified
True/False
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) increased reliance on computers for record keeping
B) development of the EOQ model
C) the need for inventory control systems
D) the emergence of ERP systems
E) accounting systems
Correct Answer
verified
Multiple Choice
A) 2
B) 50
C) 100
D) 150
E) 200
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 340
B) 350
C) 380
D) 400
E) 590
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Showing 1 - 20 of 84