If the cost estimate for a project is a basis for contract awards and performance reporting, it should be a(n) _____ estimate and as accurate as possible.


A) budgetary
B) definitive  
C) rough order of magnitude
D) analogous

Correct Answer

verifed

verified

_____ helps develop an accurate projection of a project's financial expenses and benefits.


A) Critical path analysis
B) Fast tracking  
C) Life cycle costing
D) Crashing

Correct Answer

verifed

verified

A schedule performance index of one means that the project is on schedule.

Correct Answer

verifed

verified

The budget is one of the three values of earned value management and is also known as _____.


A) earned value
B) actual cost  
C) indirect cost
D) planned value

Correct Answer

verifed

verified

Intangible costs can be easily measured in monetary terms.

Correct Answer

verifed

verified

A _____ estimate is used for making many purchasing decisions for which accurate estimates are required and for estimating final project costs.


A) budgetary
B) definitive  
C) rough order of magnitude
D) final

Correct Answer

verifed

verified

Which of the following is an input of the process of controlling costs?


A) Cost forecasts
B) Work performance data  
C) Change requests
D) Scope baseline

Correct Answer

verifed

verified

Which of the following is true of contingency reserves?


A) They allow for future situations that can be partially planned for. 
B) They are also known as unknown unknowns. 
C) They are not included in a cost baseline. 
D) They allow for dollar amounts to be used to cover existing, fixed costs.

Correct Answer

verifed

verified

The main outputs of the _____ process are a cost performance baseline, project funding requirements, and project document updates.

Correct Answer

verifed

verified

The ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity is known as the _____.

Correct Answer

verifed

verified

rate of pe...

View Answer

In a bottom-up estimate, the size of the individual work items is one of the factors that drives the accuracy of the estimates.

Correct Answer

verifed

verified

The project management plan and project funding requirements are inputs of the process of controlling costs.

Correct Answer

verifed

verified

The additional percentage or dollar amount by which actual costs exceed estimates is known as a(n) _____.

Correct Answer

verifed

verified

_____ costing helps to see a big-picture view of the cost of a project throughout its life cycle.

Correct Answer

verifed

verified

If cost variance is a positive number, it means that performing the work costs more than planned.

Correct Answer

verifed

verified

Project cost estimates are allocated to work items which are based on the activities in the _____ for the project.

Correct Answer

verifed

verified

work break...

View Answer

The primary output of the planning cost management process is a change request.

Correct Answer

verifed

verified

A cost estimation tool which involves estimating individual work items or activities and summing them to get a project total is known as a(n) _____ estimate.


A) budgetary
B) parametric  
C) bottom-up
D) analogous

Correct Answer

verifed

verified

Project managers must conduct cash flow analysis to determine _____.

Correct Answer

verifed

verified

When deciding what projects to invest in or continue, one should include sunk costs.

Correct Answer

verifed

verified