Cause-and-effect diagrams help you find the ____________________ cause of quality problems.

Correct Answer

verifed

verified

Project management software offers color ____________________ as well as numerous reports to show schedule performance information.

Correct Answer

verifed

verified

In the context of earned value management,the ____________________ is the percentage of actual work completed divided by the percentage of work planned to have been completed at any given time.

Correct Answer

verifed

verified

rate of performance
...

View Answer

Contract ____ includes the contract itself along with requested unapproved contract changes and approved change requests.


A) authorization
B) review
C) documentation
D) negotiation

Correct Answer

verifed

verified

The cost ____________________,performance reports,change requests,and project funding requirements are inputs to the cost-control process.

Correct Answer

verifed

verified

Project teams sometimes use ____-unplanned responses to risk events-when they do not have contingency plans in place.


A) work charts
B) work flows
C) work processes
D) workarounds

Correct Answer

verifed

verified

Earned value (EV)is an estimate of the value of physical work that is yet to be completed.

Correct Answer

verifed

verified

A red diamond on the tracking Gantt chart represents a slipped milestone.

Correct Answer

verifed

verified

Provide a definition for a control chart and describe how control charts are used.

Correct Answer

verifed

verified

A control chart is a graphic display of ...

View Answer

You may only use earned value management at a summary level.

Correct Answer

verifed

verified

Project risk management stops with the initial risk analysis.

Correct Answer

verifed

verified

Projects should have a change-control system that defines procedures for changing the cost baseline.

Correct Answer

verifed

verified

You cannot control the scope of a project unless you have first clearly defined the scope and set a scope verification process in place.

Correct Answer

verifed

verified

The main monitoring and controlling task performed as part of project cost management is ____ control.


A) time
B) schedule
C) scope
D) cost

Correct Answer

verifed

verified

Evaluation of any change to a project should include an impact analysis.

Correct Answer

verifed

verified

By adding all of the ____ for all project activities,you can determine how the project as a whole is performing and forecast both when it will be completed and how much it will cost at completion.


A) earned values
B) actual costs
C) planned values
D) cost variances

Correct Answer

verifed

verified

Which of the following actions will most likely improve team productivity?


A) Set the highest performance level from the start.
B) Establish regular, effective meetings.
C) Chastise team members for being lazy and careless.
D) Assign fault to the person who caused a problem.

Correct Answer

verifed

verified

The main procurement management task performed to monitor and control projects is administering the ____.


A) vision
B) contract
C) charter
D) project platform

Correct Answer

verifed

verified

____ change orders are oral or written acts or omissions by someone with actual or apparent authority that can be construed to have the same effect as a written change order.


A) Virtual
B) Non-binding
C) Apparent
D) Constructive

Correct Answer

verifed

verified

Describe the process of monitoring and controlling project work.

Correct Answer

verifed

verified

Project changes are inevitable,so it is ...