Filters
Question type

Study Flashcards

_____________ systems involve reporting, controlling, and recording changes to the project baseline.

Correct Answer

verifed

verified

Change management
Explanation: Because c...

View Answer

The first step in the risk management process is risk assessment.

Correct Answer

verifed

verified

Which of the following is NOT involved in risk control?


A) Executing the risk response strategy
B) Initiating contingency plans
C) Establishing a change control system
D) Establishing contingency funds
E) Watching for new risks

Correct Answer

verifed

verified

According to the Failure Mode and Effects Analysis (FMEA), Impact x Probability x Detection = __________.

Correct Answer

verifed

verified

risk value
Explanation: Failur...

View Answer

A risk profile is a list of questions that have been developed and refined from previous, similar projects.

Correct Answer

verifed

verified

Adopting proven technology instead of experimental technology is an example of mitigating a risk.

Correct Answer

verifed

verified

One common mistake made early in the risk identification process is to


A) Not consider all possibilities.
B) Encourage participants be over optimistic.
C) Support participants being over pessimistic.
D) Focus on consequences and not on the events that could produce consequences.
E) Give too much attention to past events.

Correct Answer

verifed

verified

________ reserves are identified for specific work packages and are distributed by the project manager and the team members.

Correct Answer

verifed

verified

Budget
Explanation: These reserves are i...

View Answer

Contingency funding is made up of budget reserves and management reserves.

Correct Answer

verifed

verified

Most changes on a project are related to


A) Scope Changes.
B) Improvement Changes.
C) Implementing Contingency Plans.
D) All of these choices are correct.

Correct Answer

verifed

verified

Change management systems are designed to accomplish all of the following EXCEPT


A) Track all changes that are to be implemented.
B) Review, evaluate, and approve/disapprove proposed changes formally.
C) Identify expected effects of proposed changes on schedule and budget.
D) Reflect scope changes in baseline and performance measures.
E) All of these are examples of what change management systems are designed to accomplish.

Correct Answer

verifed

verified

Based on the following, which event should you be most concerned about? Risk Event Likelihood Impact Bad weather 2 3 Design flaw 3 5 Accident 1 5 Shipment delay 2 2 Power outage 1 5


A) Bad weather
B) Design flaw
C) Accident
D) Shipment delay
E) Power outage

Correct Answer

verifed

verified

Flooding would be devastating to the project; however, it is very unlikely.The project manager is most likely to __________ this risk.

Correct Answer

verifed

verified

retain
Explanation: Some risks are so la...

View Answer

This response is used to remove any uncertainly associated with an identified Opportunity.


A) Exploit
B) Share
C) Enhance
D) Accept

Correct Answer

verifed

verified

Which of the following activities might you consider adding a time buffer to?


A) Activities with severe risks
B) Merge activities that are prone to delays
C) Activities with scarce resources
D) Noncritical activities with very little slack
E) You might consider adding a time buffer to any of these activities.

Correct Answer

verifed

verified

Responses to all identifiable risks should be a top priority for the project manager.

Correct Answer

verifed

verified

What is a "trigger" and why is it important when planning contingencies?

Correct Answer

verifed

verified

A trigger is an event or point in time w...

View Answer

Performance bonds, warranties, and guarantees are financial instruments used to share risk.

Correct Answer

verifed

verified

Showing 81 - 98 of 98

Related Exams

Show Answer