Filters
Question type

Study Flashcards

One of the general reasons why project costs may exceed estimated prices is takeoff quantities are too high.

Correct Answer

verifed

verified

All of the following are reasons why project costs may exceed estimated prices EXCEPT ________.


A) actual productivity does not meet anticipated productivity.
B) subcontractors or materials suppliers fail to meet obligations.
C) takeoff quantities are too high.
D) takeoff quantities are too low.

Correct Answer

verifed

verified

C

A sorted list of items that are part of an estimate is referred to as the ____.


A) summary
B) collection
C) recap
D) capstone

Correct Answer

verifed

verified

C

Where union labor is used, the wage rate will be the rate that is found ____.


A) in federal compensation guidelines
B) in the local union agreement for the craft involved
C) in the national union agreement for the craft involved
D) in the national standard compensation tables

Correct Answer

verifed

verified

The process of pricing an estimate can be divided into four stages.

Correct Answer

verifed

verified

When a contract states that the contractor will be reimbursed all project costs by the owner plus an added amount for profit, this is known as a ____.


A) contingency
B) cost contract
C) lump-sum
D) cost-plus contract

Correct Answer

verifed

verified

The nature of the recap breakdown depends on the type of work involved in the project and the type of contract the contractor will be entering into with the owner.

Correct Answer

verifed

verified

The contractor has little or no influence over job factors.

Correct Answer

verifed

verified

The categories considered in the pricing of an estimate include all of the following EXCEPT _______.


A) labor
B) subcontractors
C) job overheads
D) productivity

Correct Answer

verifed

verified

Almost all price quotations received from material suppliers will have terms and conditions attached to them.

Correct Answer

verifed

verified

When the recap is complete, prices of each trade will be presented in ____ form, which facilitates easier evaluation of the estimate.


A) summary
B) standard
C) generic
D) basic

Correct Answer

verifed

verified

A

The risk of bankruptcy by a subtrade can be reduced by calling for ____ from subtrades.


A) performance bonds
B) risk bonds
C) surety bonds
D) conformance bonds

Correct Answer

verifed

verified

Most project specifications provide detailed descriptions of the materials to be supplied by the ____.


A) owner
B) materials supplier
C) contractor
D) subcontractor

Correct Answer

verifed

verified

In general, all subtrades offer lump-sum bids.

Correct Answer

verifed

verified

A price quoted as ____, in the absence of a definition to the contrary, is interpreted to mean the price includes delivery to the site but the contractor is responsible for the cost of any unloading requirements at the site.


A) C.O.D.
B) F.O.B.
C) C.I.F.
D) D.D.U.

Correct Answer

verifed

verified

There is a high risk of cost overruns with material estimates.

Correct Answer

verifed

verified

The unit prices used in an estimate are generally obtained directly from the suppliers.

Correct Answer

verifed

verified

The reason for preparing the recap is to bring together all work of a similar nature so that the estimator can concentrate on the needs of one trade at a time.

Correct Answer

verifed

verified

Materials are usually quoted including taxes.

Correct Answer

verifed

verified

The most common reason for failure to perform by a subtrade is the financial collapse of the subtrade.

Correct Answer

verifed

verified

Showing 1 - 20 of 20

Related Exams

Show Answer