Filters
Question type

The usual method for computing storage volume is the elevation-area method.

Correct Answer

verifed

verified

The ____________________ is the volume of water temporarily stored in a detention basin during a rainfall event.

Correct Answer

verifed

verified

impoundment

A rainfall event that exceeds the design storm rainfall could ____.


A) drain out the main outlet
B) cause the impoundment level to exceed maximum elevation
C) damage the outlets
D) decrease the impoundment level

Correct Answer

verifed

verified

The primary purpose of an emergency spillway is to control any eventual overtopping of the detention basin by directing the flow in a harmless direction.

Correct Answer

verifed

verified

A multiple-stage outlet contains more than one outlet structure.

Correct Answer

verifed

verified

What is the term for computing the outflow hydrograph when the inflow hydrograph is known?


A) attenuation
B) routing
C) continuity
D) Kinematic Wave Method

Correct Answer

verifed

verified

Impounded water in a detention basin is released quickly through the outlet structure.

Correct Answer

verifed

verified

Emergency spillways consist of an additional ____________________ set at an elevation higher than all others so that water will not enter unless the impoundment level has risen higher than anticipated for the design storm.

Correct Answer

verifed

verified

The Modified Puls Method method of reservoir routing relies on the so-called ____________________, which is a statement of conservation of the mass of water entering and leaving the reservoir or impoundment.

Correct Answer

verifed

verified

continuity equation

When runoff enters a detention basin and is temporarily stored and then exits through the outlet structure, the peak rate of outflow is____________________ the peak rate of inflow.

Correct Answer

verifed

verified

Volume for underground detention basins is computed using which method?


A) elevation-area method
B) average end-area method
C) end-area elevation method
D) average method

Correct Answer

verifed

verified

The primary purpose of an emergency spillway is to provide a way for excessive water in the impoundment to exit safely, thus preventing a(n) ____________________ of the berm.

Correct Answer

verifed

verified

What is the calculation called for a series of hypothetical water levels in an impoundment and their corresponding discharge through an orifice?


A) single-stage outlet
B) impoundment
C) discharge rating
D) berm

Correct Answer

verifed

verified

Separate grassed channels are used for major detention basins with large maximum impoundments because this is the safest type of emergency spillway.

Correct Answer

verifed

verified

A single-stage outlet is so called because it allows water to flow through ____ opening(s) .


A) one
B) two
C) three
D) four

Correct Answer

verifed

verified

A

Showing 1 - 15 of 15