What is the Concurrent Engineering Approach and why should project managers be aware of it?

Correct Answer

verifed

verified

The chainlike sequence of finish-to-star...

View Answer

The likelihood the original critical path(s) will change once the project is initiated is referred to as


A) flexibility.
B) resilience.
C) sensitivity.
D) concurrent engineering.
E) rigidity.

Correct Answer

verifed

verified

The delaying of any activity on the __________ will delay the completion of the project by the same amount.


A) network
B) critical path
C) WBS
D) gantt chart
E) responsibility assignment matrix

Correct Answer

verifed

verified

Which of the following is NOT one of the basic rules to follow when developing project networks?


A) An activity cannot begin until all preceding activities have been completed.
B) Each activity must have a unique identification number.
C) Conditional statements are allowed but looping statements are not allowed.
D) An activity identification number must be larger than that of any preceding activities.
E) Networks flow from left to right.

Correct Answer

verifed

verified

C

Consider the following table of activities A through G in which A is the start node and G is the stop node.


A) 26
B) 27
C) 28
D) 29
E) 30

Correct Answer

verifed

verified

A(n) _________ activity has more than one dependency arrow flowing from it.


A) parallel
B) critical path
C) burst
D) merge
E) independent

Correct Answer

verifed

verified

A(n) ________ is the minimum amount of time a dependent activity must be delayed to begin or end.


A) saunter
B) lag
C) lead
D) wane
E) hobble

Correct Answer

verifed

verified

B

Consider the following table of activities A through G in which A is the start node and G is the stop node.


A) A-B-F-G, 31
B) A-D-E-G, 22
C) A-D-E-G, 25
D) A-C-E-G. 20
E) A-C-D-G, 28

Correct Answer

verifed

verified

Which of the following does NOT help describe a project network?


A) A graphic display of the flow and sequence of work through the project
B) Provides the basis for scheduling labor and equipment
C) Gives the times when activities can start and finish and when they can be delayed
D) Highlights major deliverables and identifies their completion dates
E) Identifies critical activities

Correct Answer

verifed

verified

A purchasing agent is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days. Fortunately, the purchasing agent has 10 days of slack; however, he shares this slack with the hardware installer. He will have to let the contractor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. The purchasing agent and the installer share 10 days of


A) free slack.
B) shared slack.
C) total slack.
D) critical slack.
E) functional slack.

Correct Answer

verifed

verified

A _________ activity is one that has more than one activity immediately preceding it.


A) Burst
B) Merge
C) Parallel
D) Slack
E) Dangling

Correct Answer

verifed

verified

Activities that must immediately follow a given activity are called ________ activities.


A) predecessor
B) successor
C) prior
D) immediate
E) concurrent or parallel

Correct Answer

verifed

verified

If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?


A) Check to see which activities cost the least.
B) Check to see which activities have the longest duration.
C) Check to see which activities are on the critical path.
D) Check to see which activities have the most slack.
E) Check to see which activities have the highest risk.

Correct Answer

verifed

verified

A(n) ________ activity has more than one successor activity.


A) parallel
B) merge
C) burst
D) critical
E) dangling

Correct Answer

verifed

verified

The ________ calculates the earliest times that activities can start or finish.


A) backward pass
B) universal pass
C) forward pass
D) concurrent pass
E) parallel pass

Correct Answer

verifed

verified

The amount of time an activity can be delayed and yet not delay the project is termed


A) total slack.
B) free slack.
C) critical float.
D) float pad.
E) slip pad.

Correct Answer

verifed

verified

Lags can be used to constrain the start and finish of an activity.

Correct Answer

verifed

verified

True

Consider the following table of activities A through G in which A is the start node and G is the stop node.


A) 0
B) 15
C) 21
D) 30
E) 46

Correct Answer

verifed

verified

Consider the following table of activities A through G in which A is the start node and G is the stop node.


A) 0
B) 2
C) 4
D) 15
E) 17

Correct Answer

verifed

verified

________ slack is the amount of time an activity can be delayed without delaying any immediately following (successor) activity can never be negative.


A) Free
B) Static
C) Total
D) Dynamic
E) Flexible

Correct Answer

verifed

verified