Multiple Choice
A) flexibility.
B) resilience.
C) sensitivity.
D) concurrent engineering.
E) rigidity.
Correct Answer
verified
Multiple Choice
A) network
B) critical path
C) WBS
D) gantt chart
E) responsibility assignment matrix
Correct Answer
verified
Multiple Choice
A) An activity cannot begin until all preceding activities have been completed.
B) Each activity must have a unique identification number.
C) Conditional statements are allowed but looping statements are not allowed.
D) An activity identification number must be larger than that of any preceding activities.
E) Networks flow from left to right.
Correct Answer
verified
Multiple Choice
A) 26
B) 27
C) 28
D) 29
E) 30
Correct Answer
verified
Multiple Choice
A) parallel
B) critical path
C) burst
D) merge
E) independent
Correct Answer
verified
Multiple Choice
A) saunter
B) lag
C) lead
D) wane
E) hobble
Correct Answer
verified
Multiple Choice
A) A-B-F-G, 31
B) A-D-E-G, 22
C) A-D-E-G, 25
D) A-C-E-G. 20
E) A-C-D-G, 28
Correct Answer
verified
Multiple Choice
A) A graphic display of the flow and sequence of work through the project
B) Provides the basis for scheduling labor and equipment
C) Gives the times when activities can start and finish and when they can be delayed
D) Highlights major deliverables and identifies their completion dates
E) Identifies critical activities
Correct Answer
verified
Multiple Choice
A) free slack.
B) shared slack.
C) total slack.
D) critical slack.
E) functional slack.
Correct Answer
verified
Multiple Choice
A) Burst
B) Merge
C) Parallel
D) Slack
E) Dangling
Correct Answer
verified
Multiple Choice
A) predecessor
B) successor
C) prior
D) immediate
E) concurrent or parallel
Correct Answer
verified
Multiple Choice
A) Check to see which activities cost the least.
B) Check to see which activities have the longest duration.
C) Check to see which activities are on the critical path.
D) Check to see which activities have the most slack.
E) Check to see which activities have the highest risk.
Correct Answer
verified
Multiple Choice
A) parallel
B) merge
C) burst
D) critical
E) dangling
Correct Answer
verified
Multiple Choice
A) backward pass
B) universal pass
C) forward pass
D) concurrent pass
E) parallel pass
Correct Answer
verified
Multiple Choice
A) total slack.
B) free slack.
C) critical float.
D) float pad.
E) slip pad.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 0
B) 15
C) 21
D) 30
E) 46
Correct Answer
verified
Multiple Choice
A) 0
B) 2
C) 4
D) 15
E) 17
Correct Answer
verified
Multiple Choice
A) Free
B) Static
C) Total
D) Dynamic
E) Flexible
Correct Answer
verified