Without a __________ budget a good project schedule and cost control are impossible.


A) time-phased
B) project cost baseline
C) definitive
D) forecasted
E) firm

Correct Answer

verifed

verified

Having too few programmers and too many engineers is an example of a people resource constraint.

Correct Answer

verifed

verified

Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation?


A) Activity delays
B) Project delays
C) Difficulty in taking quick corrective action
D) Increase costs
E) Scope creep

Correct Answer

verifed

verified

After constructing a project network based on technical constraints and reviewing resource requirements throughout the project, a project manager realizes many peaks and valleys in regard to resource usage. At one point the project manager needs 6 developers, but top management has made it very clear that she will not have access to more than 4. Classify this project in terms of the scheduling problem. What are the project manager's options at this point?

Correct Answer

verifed

verified

This project is classified as a resource...

View Answer

A project budget report is showing our project as spending $82,000 against a budgeted amount of $85,000. We can assume that everything is going as planned and that we are under budget.

Correct Answer

verifed

verified

If resources are truly limited and activity time estimates are accurate, the resource-constrained schedule will materialize as the project is implemented, not the time-constrained schedule.

Correct Answer

verifed

verified

In terms of project classification, ________ constrained means that project duration is fixed and resources are flexible.


A) time
B) people
C) material
D) resource
E) equipment

Correct Answer

verifed

verified

What are the impacts of resource-constrained scheduling?

Correct Answer

verifed

verified

Like leveling schedules, the limited res...

View Answer

Consider the following table of activities A through E in which A is the start node and E is the stop node.


A) Monday, May 25, 2020
B) Sunday, May 24, 2020
C) Friday, May 29, 2020
D) Tuesday, June 2, 2020
E) Monday, June 1, 2020

Correct Answer

verifed

verified

When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is called


A) outsourcing.
B) redistribution of projects.
C) project allocation.
D) task sharing.
E) referring.

Correct Answer

verifed

verified

When considering the sequence and timing of activities, which of the following is NOT one of the types of project network constraints?


A) Physical
B) Technical
C) Resource
D) Time
E) All of these are types of constraints that could impact structure of the project network.

Correct Answer

verifed

verified

When developing project networks, which of the following is not a reason for delineating technical dependencies first before doing resource dependencies?


A) The interrelationships and interactions among time and resource constraints are complex for even small project networks.
B) Resource availability may not be known until the initial schedule is completed.
C) Even if resources are known, one cannot assess the impact of limited resources until a resource-neutral schedule is created.
D) An effort to examine the interactions between technical / logical constraints and resource limitations frequently uncovers surprising problems.
E) All of these alternatives are reasons for delineating technical dependencies first before doing resource dependencies.

Correct Answer

verifed

verified

In a resource-constrained project the third priority in assigning resources is usually given to activities with the


A) smallest duration.
B) least slack.
C) most slack.
D) lowest identification number.
E) highest cost.

Correct Answer

verifed

verified

When there are not enough people, money, and / or equipment available for a project it is known as being


A) managerially resourceful.
B) operationally successful.
C) resource constrained.
D) delayed without prejudice.
E) project constrained.

Correct Answer

verifed

verified