A) Not increasing risk as activities are initially crashed.
B) Having potential for real cost savings when crashed.
C) Having potential for significant time savings when crashed.
D) Having potential for flexible scheduling.
E) All of these alternatives are correct.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) activity
B) resource
C) work package
D) task
E) milestone
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Splitting and stacking a cord of wood
B) Developing new software
C) Harvesting a crop by hand
D) Building a cabin
E) Moving to a new house
Correct Answer
verified
Multiple Choice
A) Establish a core project team
B) Fast-tracking
C) Reduce project scope
D) Compromise quality
E) Use critical-chain project management
Correct Answer
verified
Multiple Choice
A) overtime is associated with additional costs of coordination and communication.
B) sustained overtime work by salaried employees may incur burnout.
C) productivity is reduced the longer one is working.
D) more hours results in higher expenses if paying workers hourly.
E) continued overtime can lead to a higher turnover rate.
Correct Answer
verified
Multiple Choice
A) resources
B) overtime
C) contractors
D) outsourcing
E) activities
Correct Answer
verified
Multiple Choice
A) Design flaws.
B) Marketing promises the product to the customer within three months.
C) The president announces availability of the product in one year.
D) The chief technology officer says, "finish the projects in six months or start packing."
E) Intense global competition.
Correct Answer
verified
Multiple Choice
A) Two critical paths, only C is noncritical, insensitive
B) Three critical paths, only E is noncritical, sensitive
C) Four critical paths, only D is noncritical, sensitive
D) Three critical paths, only C is noncritical, sensitive
E) Two critical paths, only E is noncritical, insensitive
Correct Answer
verified
Multiple Choice
A) expedited
B) accelerated
C) crash
D) optimistic
E) optimal
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) direct
B) budgeted
C) accumulated
D) indirect
E) time-phased
Correct Answer
verified
Multiple Choice
A) 0
B) 1
C) 2
D) 3
E) 4
Correct Answer
verified
Multiple Choice
A) Assign additional staff and equipment
B) Establish a core team
C) Do it twice-fast and correctly
D) Reduce project scope
E) Compromise quality
Correct Answer
verified
Multiple Choice
A) budgeted
B) time-limited
C) crash
D) minimal
E) early completion
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) fast-tracking.
B) use critical-chain project management.
C) reduce project scope.
D) compromise quality.
E) do it twice-fast and correctly.
Correct Answer
verified
Multiple Choice
A) imposed project deadlines.
B) time to market.
C) unforeseen project delays.
D) high overhead.
E) incentive contracts.
Correct Answer
verified
Showing 61 - 80 of 106