An insensitive project network has the benefit of:


A) Not increasing risk as activities are initially crashed.
B) Having potential for real cost savings when crashed.
C) Having potential for significant time savings when crashed.
D) Having potential for flexible scheduling.
E) All of these alternatives are correct.

Correct Answer

verifed

verified

Indirect costs generally represent overhead costs such as supervision, administration, consultants, and interest.

Correct Answer

verifed

verified

Direct costs are assignable directly to a particular ________.


A) activity
B) resource
C) work package
D) task
E) milestone

Correct Answer

verifed

verified

The total cost for each time unit of a project is the sum of labor, materials, and equipment.

Correct Answer

verifed

verified

Which of the following projects would be least benefited if additional resources were added?


A) Splitting and stacking a cord of wood
B) Developing new software
C) Harvesting a crop by hand
D) Building a cabin
E) Moving to a new house

Correct Answer

verifed

verified

When it is necessary to reduce project duration and resources are constrained, which of the following is NOT a reasonable option?


A) Establish a core project team
B) Fast-tracking
C) Reduce project scope
D) Compromise quality
E) Use critical-chain project management

Correct Answer

verifed

verified

All of the following are disadvantages of scheduling overtime EXCEPT


A) overtime is associated with additional costs of coordination and communication.
B) sustained overtime work by salaried employees may incur burnout.
C) productivity is reduced the longer one is working.
D) more hours results in higher expenses if paying workers hourly.
E) continued overtime can lead to a higher turnover rate.

Correct Answer

verifed

verified

When you schedule ________ exclusively, you avoid the additional costs of coordination and communication when new people are added.


A) resources
B) overtime
C) contractors
D) outsourcing
E) activities

Correct Answer

verifed

verified

Which of the following is not likely to result in an imposed deadline?


A) Design flaws.
B) Marketing promises the product to the customer within three months.
C) The president announces availability of the product in one year.
D) The chief technology officer says, "finish the projects in six months or start packing."
E) Intense global competition.

Correct Answer

verifed

verified

Consider the following table of activities that describes a project network. After all the crashing you can do is done (assuming you can crash only one activity at a time) , how many paths are critical? Which activities remain noncritical? Would you characterize this network as sensitive or insensitive?


A) Two critical paths, only C is noncritical, insensitive
B) Three critical paths, only E is noncritical, sensitive
C) Four critical paths, only D is noncritical, sensitive
D) Three critical paths, only C is noncritical, sensitive
E) Two critical paths, only E is noncritical, insensitive

Correct Answer

verifed

verified

The shortest possible time an activity can be completed realistically is called ___­­­_____ time.


A) expedited
B) accelerated
C) crash
D) optimistic
E) optimal

Correct Answer

verifed

verified

Crashing activities on a project network that is sensitive could increase the risk of the project being late.

Correct Answer

verifed

verified

The higher the cost slope of an activity the lower the cost to reduce its duration.

Correct Answer

verifed

verified

Overhead costs such as supervision, administration, consultants, and interest are examples of ________ project costs.


A) direct
B) budgeted
C) accumulated
D) indirect
E) time-phased

Correct Answer

verifed

verified

Consider the following table of activities that describes a project network. How much reduction in project duration could you get from crashing activity C?


A) 0
B) 1
C) 2
D) 3
E) 4

Correct Answer

verifed

verified

Which of the following is NOT a technique for accelerating project completion when resources are not constrained?


A) Assign additional staff and equipment
B) Establish a core team
C) Do it twice-fast and correctly
D) Reduce project scope
E) Compromise quality

Correct Answer

verifed

verified

The direct cost for completing an activity as early as possible is called its ________ cost.


A) budgeted
B) time-limited
C) crash
D) minimal
E) early completion

Correct Answer

verifed

verified

How would you calculate an activity's slope and what does it represent?

Correct Answer

verifed

verified

An activity's slope is the cos...

View Answer

When a project manager must reduce project duration but resources are constrained, creating a software program that will have less functionality than originally planned or building a house without the bonus room and the basement that the owner originally specified in the plans would both be examples of


A) fast-tracking.
B) use critical-chain project management.
C) reduce project scope.
D) compromise quality.
E) do it twice-fast and correctly.

Correct Answer

verifed

verified

Intense global competition and rapid technological advances create pressure to develop projects rapidly. This is an example of reducing project duration caused by


A) imposed project deadlines.
B) time to market.
C) unforeseen project delays.
D) high overhead.
E) incentive contracts.

Correct Answer

verifed

verified