A) A for 2 days
B) B for 2 days
C) C for 1 day
D) B for 1 day
E) A for 1 day
Correct Answer
verified
True/False
Correct Answer
verified
Essay
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) run by the rise.
B) rise by the run.
C) crash cost by the normal cost.
D) normal cost by the crash cost.
E) indirect cost by direct cost.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) Find the activity with the lowest crash cost
B) Calculate the optimum cost-time point
C) Calculate the crash point
D) Identify the critical path
E) Find the activity with the highest crash cost
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $50
B) $100
C) $150
D) $300
E) $30
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) From 60 days to 50 days
B) From 60 days to 40 days
C) From 60 days to 30 days
D) From 60 days to 20 days
E) From 60 days to 10 days
Correct Answer
verified
Multiple Choice
A) Yes, sensitive. 30 days.
B) Yes, sensitive. 25 days.
C) No, insensitive. 25 days.
D) No, insensitive. 30 days.
E) Neither sensitive nor insensitive. 35 days.
Correct Answer
verified
Multiple Choice
A) decrease
B) increase
C) reduce
D) expand
E) approximate
Correct Answer
verified
Multiple Choice
A) least steep slope.
B) earliest start time.
C) longest duration.
D) most steep slope.
E) largest crash time.
Correct Answer
verified
Multiple Choice
A) A
B) B
C) D
D) F
E) G
Correct Answer
verified
Multiple Choice
A) Increase risk of delaying the project.
B) Improve cost-time crashing success.
C) Reduce scheduling flexibility.
D) Increase risk of delaying the project and reduce scheduling flexibility.
E) Increase risk of delaying the project but improve cost-time crashing success.
Correct Answer
verified
Multiple Choice
A) labor
B) direct
C) project
D) overhead
E) interest
Correct Answer
verified
Multiple Choice
A) elastic.
B) fully consumed.
C) inherently risky.
D) sensitive.
E) insensitive.
Correct Answer
verified
Multiple Choice
A) Reduce project scope
B) Have owner take more responsibility
C) Move the completion date further out
D) Brainstorm cost savings options
E) Outsource project activities
Correct Answer
verified
Multiple Choice
A) run rate
B) rise rate
C) rise / run rate
D) slope
E) daily cost
Correct Answer
verified
Showing 1 - 20 of 106
Related Exams