Scenario 6.1 El Gran Raton, the producers of the finest carpincho wallets in all of Argentina, examined their production process in the form of a value stream map, displayed below. Scenario 6.1 El Gran Raton, the producers of the finest carpincho wallets in all of Argentina, examined their production process in the form of a value stream map, displayed below.     Daniel Penfield artist -In Scenario 6.1, what does the triangle between Process A and Process B represent? A)  WIP B)  takt C)  OWMM D)  kanban Daniel Penfield artist -In Scenario 6.1, what does the triangle between Process A and Process B represent?


A) WIP
B) takt
C) OWMM
D) kanban

Correct Answer

verifed

verified

Burdell Salad Dressings uses a Kanban system. The daily demand for corrugated boxes used in packaging its dressings is 300 boxes. The average waiting time for a container of boxes is 0.25 day. The processing time for a container of boxes is 0.1 day, and a container holds 10 boxes. If Burdell wishes to use a 5% policy variable, what is the level of work in process inventory in their plant?

Correct Answer

verifed

verified

k = blured image = blured image = 11.025 → 12 containe...

View Answer

Which one of the following is an advantage of lean systems?


A) Lean systems reduce equipment needs by using larger lot sizes.
B) Lean systems can be implemented in any production environment.
C) Lean systems result in a decrease in safety stock and work-in-process inventory.
D) Lean systems result in an increase in manufacturing lead times.

Correct Answer

verifed

verified

Champion Cooling Company uses a kanban system at their two locations in the Oklahoma City Metroplex. The daily demand for fans is 2,000 at each location and management insists on using the same alpha level (0.1) at both locations. Location Reno uses containers that hold 20 items and takes 0.04 of a day to process a container. It takes 0.07 of a day to get a container filled and for it to wait during its cycle. Location Western uses containers that hold 24 items and takes 0.02 of a day to process a container. It takes 0.08 of a day to get a container filled and for it to wait during its cycle. Which location has the higher level of inventory? Assume that both locations round up to the next highest integer number of containers.

Correct Answer

verifed

verified

kReno = blured image = blured image = 12.1 → 12
WIPRen...

View Answer

Regarding the Eight Types of Waste that must be eliminated to implement lean systems, using expensive high precision equipment when a simpler machine would suffice is part of which general waste category?


A) Motion
B) Overproduction
C) Inappropriate Processing
D) Defects

Correct Answer

verifed

verified

In the Toyota Production System, when a work station needs more material, it is obvious to both the worker and the supplier that material is needed. Further, the amount needed must be understood as well as the delivery time for replenishment.

Correct Answer

verifed

verified

JIT II refers to a form of supplier partnership that places a supplier representative, who is empowered to plan and schedule the replenishment of materials from the supplier, in the customer's plant on a full-time basis.

Correct Answer

verifed

verified

Regarding the Eight Types of Waste that must be eliminated to implement lean systems, manufacturing an item before it is needed is part of which general waste category?


A) Inappropriate Processing
B) Waiting
C) Inventory
D) Overproduction

Correct Answer

verifed

verified

What is the difference between the "push" and "pull" methods of material flow? Which method does lean systems use?

Correct Answer

verifed

verified

With the pull method, customer demand (a...

View Answer

A method in which production of an item begins in advance of customer needs is called:


A) the andon method.
B) the pull method.
C) the jidoka method.
D) the push method.

Correct Answer

verifed

verified

In lean systems, if a defective product is found, which of the following is generally not done?


A) The production line is stopped.
B) The defective unit is passed on to the next workstation.
C) The defective unit is returned to the worker responsible for creating the defect.
D) The production line is made aware of the problem without necessarily stopping the line.

Correct Answer

verifed

verified

A ________ is based on both a withdrawal card and a production-order card, to control inventory quantities more closely.

Correct Answer

verifed

verified

two-card K...

View Answer

In a ________ system based on other Kanban signals, an empty space signals a need to fill it.

Correct Answer

verifed

verified

Transforming a current process design to one embodying a ________ philosophy is a constant challenge for management, often fraught with implementation issues.

Correct Answer

verifed

verified

Which one of the following statements regarding the Toyota production system is best?


A) It is particularly well suited for making irregularly used parts and customized "specials."
B) It is a "push system," with orders pushed out in anticipation of future requirements.
C) Each container has either a withdrawal or production-ordering Kanban.
D) It does not use poka yoke or 5S practices.

Correct Answer

verifed

verified

Quality at the source is a philosophy whereby defects are caught and corrected where they are created.

Correct Answer

verifed

verified

What are the supply chain implications of the lean system emphasis on small lot sizes?

Correct Answer

verifed

verified

Small lot sizes reduce average inventory...

View Answer

Lean systems use the standardization of components because standardization:


A) decreases the demand for each component.
B) increases repeatability.
C) increases lot sizes more easily.
D) decreases repeatability.

Correct Answer

verifed

verified

Heijunka is the leveling of production load by both volume and product mix.

Correct Answer

verifed

verified

The lean system concept will not work without the proper environment. Which one of the following characteristics is most common to firms that have successfully implemented a lean system?


A) uniform assembly schedules
B) specialized workforce
C) high rates of machine failures
D) longer setup times

Correct Answer

verifed

verified