Filters
Question type

Study Flashcards

Vasquez, Inc.is establishing the direct materials and direct labor standards for its leading product.Materials cost from the supplier are $5 per square foot, net of purchase discount.Freight-in amounts to $0.10 per square foot.Basic wages of the assembly line personnel are $10 per hour.Payroll taxes are approximately 20% of wages.How much is the direct labor cost standard per hour?


A) $5.00 per hour.
B) $10.00 per hour.
C) $12.00 per hour.
D) $17.10 per hour.
E) None of the answers is correct.

Correct Answer

verifed

verified

The aggregate nature of the vari ances in standard costing is a drawback in the advanced manufacturing setting that makes it difficult for man agers to determine their cause.

Correct Answer

verifed

verified

Listed below are five variances (and possible causes) that are under review by management of Knight Company.Which of the following is least likely to cause the variance indicated?


A) The need to ship goods acquired from a distant supplier via overnight carrier than via common carrier truck; material price variance.
B) The need to complete goods on a timely basis during a period of high absenteeism; labor rate variance.
C) A work-team that is very unhappy with its supervisor; labor efficiency variance.
D) The need to close a plant for two days because of blizzard conditions; material quantity variance, part no.542.
E) A malfunctioning piece of manufacturing equipment; labor efficiency variance.

Correct Answer

verifed

verified

Normal defect rates in an assembly process would be considered if a company desires to establish a series of practical manufacturing standards.

Correct Answer

verifed

verified

A statistical control chart is best used for determining:


A) direct-material price variances.
B) direct-labor variances.
C) whether a variance is favorable or unfavorable.
D) who should be held accountable for specific variances.
E) whether a particular variance should be investigated.

Correct Answer

verifed

verified

When considering whether to investigate a variance, managers should consider all of the following except the variance's:


A) size.
B) pattern of recurrence.
C) trends over time.
D) nature, namely, whether it is favorable or unfavorable.
E) controllability.

Correct Answer

verifed

verified

At the end of the accounting period, most companies close variance accounts to:


A) Raw-Material Inventory.
B) Work-in-Process Inventory.
C) Finished-Goods Inventory.
D) Cost of Goods Sold.
E) Income Summary.

Correct Answer

verifed

verified

Van Buren Frames manufactures hardwood luxury picture frames.The company uses standard costs to prepare its flexible budget.For the company's the first quarter of 20x8, direct material and direct labor standards for one of their most popular frames were as follows: Materials: 1.5 board feet per unit; $4.00 per board foot Labor: 2.0 hours per unit; $18.00 per hour During the first quarter, Van Buren produced 5,000 units of this product.At the end of the quarter, an examination of the materials records showed that the company used 7,000 board feet of materials and the direct materials cost variance was $1,750 U.Which of the following would be a logical explanation for this variance?


A) The company paid a higher price for the materials than allowed by the standards.
B) The company used greater quantity of materials than allowed by the standards.
C) The company paid a higher rate for labor than allowed by the standards.
D) The company used more labor hours than allowed by the standards.
E) None of the answers is correct.

Correct Answer

verifed

verified

Which of the following variances cannot occur together during the same accounting period?


A) Unfavorable labor rate variance and favorable labor efficiency variance.
B) Unfavorable labor efficiency variance and favorable material quantity variance.
C) Favorable labor rate variance and unfavorable total labor variance.
D) Favorable labor efficiency variance and favorable material quantity variance.
E) None of the other answers are correct, because all of these variance combinations are possible.

Correct Answer

verifed

verified

A favorable labor rate variance is created when:


A) actual labor hours worked exceed standard hours allowed.
B) actual hours worked are less than standard hours allowed.
C) actual wages paid are less than amounts that should have been paid for the number of hours worked.
D) actual units produced exceed budgeted production levels.
E) actual units produced exceed standard hours allowed.

Correct Answer

verifed

verified

Perez, Inc.recently completed 56,000 units of a product that was expected to consume four pounds of direct material per finished unit.The standard price of the direct material was $8.50 per pound.If the firm purchased and consumed 228,000 pounds in manufacturing (cost = $1,881,000) , the direct-material quantity variance would be figured as:


A) $34,000U.
B) $34,000F.
C) $57,000U.
D) $57,000F.
E) None of the answers is correct.

Correct Answer

verifed

verified

The individual generally responsible for the direct-material price variance is the:


A) sales manager.
B) production supervisor.
C) purchasing manager.
D) finance manager.
E) head of the human resources department.

Correct Answer

verifed

verified

For the quarter just ended, Halston, Inc.reported the following variances in one of its manufacturing departments: Material price variance, U Material quantity variance, F Labor efficiency variance, F Labor rate variance, negligible Machine hours efficiency, F The sum of the favorable variances exceeded the unfavorable materials price variance by a considerable amount.The quality of the output from the department was the same as usual.Halston operates very close to a JIT system for materials purchases, with virtually all material acquired during the quarter being used in manufacturing activities. Required: Is there any connection among these variances? If so, explain.

Correct Answer

verifed

verified

While a connection between these varianc...

View Answer

Product costing is the process of accumulating the costs of a production process and assigning them to the completed products.

Correct Answer

verifed

verified

Variances are computed by taking the difference between the product cost and standard cost.

Correct Answer

verifed

verified

Most companies close their variance accounts directly into Cost of Goods Sold.

Correct Answer

verifed

verified

The standard hours allowed for the work performed are:


A) 5.
B) 5.14.
C) 39,000.
D) 40,100.
E) None of the answers is correct.

Correct Answer

verifed

verified

A direct-labor efficiency variance cannot be caused by:


A) inexperienced employees.
B) poor quality raw materials.
C) employee inefficiency.
D) an out-of-date labor time standard.
E) producing fewer finished units than originally planned.

Correct Answer

verifed

verified

If a company has an unfavorable direct-material quantity variance, then:


A) the direct-material price variance is favorable.
B) the total direct-material variance is unfavorable.
C) the total direct-material variance is favorable.
D) the direct-labor efficiency variance is unfavorable.
E) any of the other answers can occur.

Correct Answer

verifed

verified

Consider the following statements: I.The standard cost per unit of materials is used to calculate a materials price variance. II.The standard cost per unit of materials is used to calculate a materials quantity variance. III.The standard cost per unit of materials cannot be determined until the end of the period. Which of the above statements is (are) true?


A) I only.
B) II only.
C) III only.
D) I and II.
E) I, II, and III.

Correct Answer

verifed

verified

Showing 21 - 40 of 78

Related Exams

Show Answer